Report for August

Report Date
August 2016

Achievements in Last Period

  • Change of project manager made to increase IS resource. 
  • Project priority changed to P1.
  • Review of project plan conducted with stakeholders.
  • Review of project risks conducted with stakeholders.
  • Modified reporting structure between Mass, IS and Estates.
  • Delivered Monthly billing development work.
  • Re-alignment of tasks between Estates and IS.
  • Milestones, budget and scope adjusted.
  • Continue scenario testing.

Issues

  • Still a significant number of issues open as a result of scenario testing. These include: EASE Authentication Deletion / Archiving Monthly Billing Work request operational report delivery from EST092.
  • There are still a significant number of Amber risks; therefore, without adequate mitigation plans.

Next Steps

  • Confirm and agree updated project plan.
  • Complete scenario testing, and move into UAT.

The project is reporting RED as a result of the budgetary increase agreed over the last month and the new project go-live date has yet to be agreed.

Project Status
RAG Status
Time
RED
Cost
RED
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
316.0 days
Activity this month
46.4 days
Activity this year
46.4 days
Activity to date
268.2 days
Estimate to complete current year
71.6 days
Estimate to complete future years
0.0 days