Report for August
- Report Date
- August 2016
Achievements in Last Period
- Change of project manager made to increase IS resource.
- Project priority changed to P1.
- Review of project plan conducted with stakeholders.
- Review of project risks conducted with stakeholders.
- Modified reporting structure between Mass, IS and Estates.
- Delivered Monthly billing development work.
- Re-alignment of tasks between Estates and IS.
- Milestones, budget and scope adjusted.
- Continue scenario testing.
Issues
- Still a significant number of issues open as a result of scenario testing. These include: EASE Authentication Deletion / Archiving Monthly Billing Work request operational report delivery from EST092.
- There are still a significant number of Amber risks; therefore, without adequate mitigation plans.
Next Steps
- Confirm and agree updated project plan.
- Complete scenario testing, and move into UAT.
The project is reporting RED as a result of the budgetary increase agreed over the last month and the new project go-live date has yet to be agreed.
- Approved budget
- 316.0 days
- Activity this month
- 46.4 days
- Activity this year
- 46.4 days
- Activity to date
- 268.2 days
- Estimate to complete current year
- 71.6 days
- Estimate to complete future years
- 0.0 days