Monthly Progress Report
- Report Date
- April 2016
Achievements
- Continue to implement remaining fixes received from Archibus/Suppliers
- Gas issue resolved details in EST080-92
- SLAs issue set up issue resolved EST080-90
- HR Concatenation has been specified EST080-93
- EST080-55 New Work order created through mobile app delivered and initially tested
- Technical protocol required upgraded for mobile devices in TEST (SHA-1 to SHA-2)
Issues
- That the existing risks regarding a small number of show stopper fixes have been resolved in time for go Live including:
- EST080-82 - Issuing Parts against a work order on the mobile
Next Steps
- Continue to implement remaining fixes received from Archibus/Suppliers
- Approve the revised proposal and costs for EST080-82 Parts work
- Receive delivery of EST080-82 Parts work from Mass
- SmartClient issue resolved 4-May and EST080-30 now Closed
- Any remaining functional issues to be resolved and JIRA work carried out, for example
- EST080-65 - Enumeration updates
- EST080-60 - Customising emails
- Once Month End Processing work is complete for all zones, and can be moved to test (EST080-87) in rediness for testing
- EST080-58 - Closing work order when survey not complete (related to monthly billing)
- All scenario testing to be run and SLA's amended where necessary
- User Guides (5) and training manuals to be 75% complete
- Weekly conference calls with Mass to ensure progress and targets for the coming weeks to continue throughout the Acceptance Testing period
- Plan Capacity and Performance Testing to be planned during UAT
Milestones
10-Jun-2016 | Full Acceptance & User Acceptance Testing |
17-Jun-2016 | Deploy to Live |
29-Jun-2016 | User Training and Rollout |
01-Jul-2016 | Live Configuration |
15-Jul-2016 | Deployment Signoff Review and Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days