Monthly Progess Report
- Report Date
- February 2016
Achievements
- Implemented any remaining fixes as received from Archibus/Suppliers
Weekly conference calls have been completed and status of issues agreed
Project Plan replanned and agreed
Project extended to June
Project Milestones agreed and approved
Planned and agreed project to complete the first Zone, before end of May
Discussed rolling out the 3 zones together at once in June
Monthly End Processing has been Specified and reviewed. Now this requires to include running PAT script in the spec
Issues
- Revised budget to be approved
Next Steps
- Revised budget to be approved
- Implement any remaining fixes to be received from Archibus/Suppliers
- Remaining functional issues to be resolved and JIRAs fixed
- Monthly End Processing spec now needs to include running a PAT script
- Agree resourcing to develop the Month End processing
- All scenario testing is run
- Weekly conference calls with Mass to ensure progress and targets for the coming weeks to continue throughout the Acceptance Testing period
- Plan full user acceptance testing during March April
- Plan Capacity and Performance Testing to be planned during UAT (in March)
Project Sponsor to approve revised budget
Milestones
Date | Milestone |
15-Apr-2016 | Acceptance / User Acceptance Testing |
26-Apr-2016 | Deploy to Live |
06-May-2016 | Live Configuration |
27-May-2016 | User Training and Rollout |
17-Jun-2016 | Deployment Signoff Review and Closure |
- Approved budget
- 180.0 days
- Activity this month
- 5.9 days
- Activity this year
- 44.4 days
- Activity to date
- 170.3 days
- Estimate to complete current year
- 46.0 days
- Estimate to complete future years
- 0.0 days