Project Update
- Report Date
- December 2015
Achievements
- Reviewed testing completed
- Revised milestones agreed
Defined full test script for both application and mobile devices based on the defined scenarios
Issues
- None
Next Steps
- Re-review the testing completed
Confirm with Mass any work not resolved
Re-confirm full test script for both application and mobile devices based on the defined scenarios
Confirm the remaining Fault Type and associated Repair Type definitions relating to the heating engineers have been agreed
- Weekly conference calls with Mass to ensure progress and targets for the coming week to continue throughout the Acceptance Testing period
- Implement remining fix to be received from Archibus
- Begin full user acceptance testing after the identified enhancements have been delivered in December/January
- Capacity and Performance Testing to be planned during UAT in January
Project Sponsor to approve revised milestones
Milestones
Date | Milestone |
18-Dec-2015 date to be agreed | Testing and Enhancements Testing |
05-Feb-2016 | Acceptance / User Acceptance Testing |
19-Feb-2016 | Deploy to Live |
04-Mar-2016 | Live Configuration |
18-Mar-2016 | User Training and Rollout |
21-Mar-2016 | Deployment Signoff Review and Closure |
- Approved budget
- 180.0 days
- Activity this month
- 2.4 days
- Activity this year
- 34.6 days
- Activity to date
- 160.5 days
- Estimate to complete current year
- 26.8 days
- Estimate to complete future years
- 0.0 days