Progress Report
- Report Date
- October 2015
Achievements
- Mass have been working on the defined enhancements, however they have not completed them to the expected timescale
- Only some of the expected enhancements have arrived
- Scenario testing has been revised and agreed for when all the enhancements arrive to allow for Acceptance Testing to follow
- Some weekly conference calls with Mass have taken place, but not consistently
Issues
- Project requires re-planned due to Mass delivery date slipping by 1 month, now Mid November before Acceptance Testing can take place
- Confirmation of project costs to be established
Next Steps
To agree the project re-plan with the expected defined enhancements
Delivery date of enhancements due in MId November
Define full test script for both application and mobile devices based on the defined scenarios
Complete the remaining Fault Type and associated Repair Type definitions relating to the heating engineers
- Weekly conference calls with Mass to ensure progress and targets for the coming week to continue throughout the Acceptance Testing period
- Confirm plan details regarding the implementation of the identified changes
- Implement fixes to be received from Archibus
- Undertake more rigorous system testing
- Begin full user acceptance testing after the identified enhancements have been delivered in Mid November
- Continue consultation with the Estates department business partners regarding fault reporting
- Capacity and Performance Testing to be planned during UAT
Since the Enhancements have been delayed by 1 month, the project has been assigned an overall RAG status of RED due to obtaining further assurance that the new milestones will be met
Milestones
Draft Milestones - Milestones to be agreed by the Project Sponsor
Date | Milestone |
13-Nov-2015 | Testing and Enhancements Testing |
11-Dec-2015 | Acceptance |
18-Dec-2015 | Live System Configuration |
08-Jan-2016 | Deployment Signoff Review and Closure |
29-Jan-2016 | User Training and Rollout |
- Approved budget
- 145.0 days
- Activity this month
- 4.4 days
- Activity this year
- 23.0 days
- Activity to date
- 148.9 days
- Estimate to complete current year
- 17.3 days
- Estimate to complete future years
- 0.0 days