Progress Report

Report Date
October 2015

Achievements

  • Mass have been working on the defined enhancements, however they have not completed them to the expected timescale
  • Only some of the expected enhancements have arrived
  • Scenario testing has been revised and agreed for when all the enhancements arrive to allow for Acceptance Testing to follow
  • Some weekly conference calls with Mass have taken place, but not consistently

Issues

  • Project requires re-planned due to Mass delivery date slipping by 1 month, now Mid November before Acceptance Testing can take place
  • Confirmation of project costs to be established

Next Steps

  • To agree the project re-plan with the expected defined enhancements

  • Delivery date of enhancements due in MId November

  • Define full test script for both application and mobile devices based on the defined scenarios

  • Complete the remaining Fault Type and associated Repair Type definitions relating to the heating engineers

  • Weekly conference calls with Mass to ensure progress and targets for the coming week to continue throughout the Acceptance Testing period
  • Confirm plan details regarding the implementation of the identified changes
  • Implement fixes to be received from Archibus
  • Undertake more rigorous system testing
  • Begin full user acceptance testing after the identified enhancements have been delivered in Mid November
  • Continue consultation with the Estates department business partners regarding fault reporting
  • Capacity and Performance Testing to be planned during UAT

Since the Enhancements have been delayed by 1 month, the project has been assigned an overall RAG status of RED  due to obtaining further assurance that the new milestones will be met

Milestones

Draft Milestones - Milestones to be agreed by the Project Sponsor

DateMilestone
13-Nov-2015Testing and Enhancements Testing
11-Dec-2015Acceptance
18-Dec-2015Live System Configuration
08-Jan-2016Deployment Signoff Review and Closure
29-Jan-2016User Training and Rollout

 

Project Status
RAG Status
Time
RED
Cost
AMBER
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
145.0 days
Activity this month
4.4 days
Activity this year
23.0 days
Activity to date
148.9 days
Estimate to complete current year
17.3 days
Estimate to complete future years
0.0 days