Monthly Progress

Report Date
August 2014

Achievements

  • Project code set up
  • Meeting with Business Lead taken place to obtain requirements
  • Plannning stage in progress

Issues

  • Whilst the planning process has commenced, it has not been possible to complete the initial planning phase due to other demands on the project manager

Next Steps

  • Complete planning / project Brief
  • Meet sponsor to agree Brief
  • Estimate project
  • Agreed Brief to WIS in September
  • Begin Business Analysis

Milestones

 

New DateMilestone

To be planned

Project Status
Activity
Approved budget
40.0 days
Activity this month
1.0 day
Activity this year
1.0 day
Activity to date
1.0 day
Estimate to complete current year
39.0 days
Estimate to complete future years
0.0 days