w/c 18th July 2016
- Scenario testing on-going
- Following observations noted after two-day supplier visit
- Completed testing of editing / publishing drawings via the SmartClient
- Functional review of BOMS console and SLA functionality
- Review of problem Types, cause Types and Repair Types
- Review of issues associated with both On-Demand and PPM
- Review of HelpDesk system related questions
- Project Plan updated and circulated
- Project go-live date to be re-schedule dto to w/c 24th October