w/c 4th July 2016

  • Confirmed business requiremenst to accommodate PAT testing for monthly billing and archiving - development scheduled to commence 8th July and into next week
  • Reviewed additional reporting requirements with IS Apps Developer - work currently scheduled to be undertaken w/c 1st August
  • System Performance Review
    • Monitoring tools set up against both the application server and the database
    • Undertook a few system tests whilst application server being montored - nothing of note to interest
    • Commenced development of Jmeter process to load test fault reporting process
    • Confirmed with supplier that there is no electronic method to load test mobile phones - so will require to organise a series of manual tests
  • Weekly project meeting
    • project plan updated by teh business lead and forwarded to supplier for reference
  • Commenced review of training startegy for each of the individual groups, namely; fault reporters, helpdesk, trades teams and supervisors
  • Commenced initial scenario testing with the HelpDesk team