w/c 7th October 2013 |
- Project Communications Related
- weekly project team meetings organised until the end of the year
- mailing list for the project team created
- monthly project board meetings organised until the end of the year
- Notification of project brief approval from WIS with a budget of 111 days
|
Andrew Stewart |
07-Oct-2013 |
|
w/c 30th September 2013 |
- Project brief submitted to WIS for approval
- Meeting held with project team to review high level business processes
- Extract of Archibus Sales Ledger fields and example dataset produced
|
Andrew Stewart |
03-Oct-2013 |
|
w/c 23rd September 2013 |
- Planning and estimation meeting held with representatives from Dev Tech, Apps Management and Tech Management
|
Andrew Stewart |
23-Sep-2013 |
|
w/c 9th September 2013 |
- First meeting of project board scheduled to review project terms of reference
|
Andrew Stewart |
12-Sep-2013 |
|
w/c 2nd September |
- Commenced work on project brief
- Meeting held with project sponsor to review project governance and terms of reference
|
Andrew Stewart |
12-Sep-2013 |