Title Description Author Post date
w/c 7th October 2013
  • Project Communications Related
    • weekly project team meetings organised until the end of the year
    • mailing list for the project team created
    • monthly project board meetings organised until the end of the year
  • Notification of project brief approval from WIS with a budget of 111 days
Andrew Stewart 07-Oct-2013
w/c 30th September 2013
  • Project brief submitted to WIS for approval
  • Meeting held with project team to review high level business processes
  • Extract of Archibus Sales Ledger fields and example dataset produced
Andrew Stewart 03-Oct-2013
w/c 23rd September 2013
  • Planning and estimation meeting held with representatives from Dev Tech, Apps Management and Tech Management
Andrew Stewart 23-Sep-2013
w/c 9th September 2013
  • First meeting of project board scheduled to review project terms of reference
Andrew Stewart 12-Sep-2013
w/c 2nd September
  • Commenced work on project brief
  • Meeting held with project sponsor to review project governance and terms of reference
Andrew Stewart 12-Sep-2013