February 2016

Report Date
February 2016

I submitted my report to Director of ITI on 8th of February.

The main conclusion is the top vendors are all producing similar technology. The main recommendation is to investigate moving to a hypervisor solution for Windows file servers. This would require further effort and if a solution was identified a budget would be necessary.

Project Status
RAG Status
Time
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Anti-Malware Provision Review
Code
ENT005
Programme
ITI - Enterprise Services (ENT)
Project Manager
Garry Scobie
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Start Date
04-Nov-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Apr-2016
Programme Priority
5