November 2015

Report Date
November 2015

A meeting with the major vendors has been scheduled for early December. This should provide a solid overview of the current market offerings and provide sufficient information to draft a paper recommending next steps.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
10.0 days
Activity this month
1.0 day
Activity this year
9.0 days
Activity to date
9.0 days
Estimate to complete current year
9.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Anti-Malware Provision Review
Code
ENT005
Programme
ITI - Enterprise Services (ENT)
Project Manager
Garry Scobie
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Start Date
04-Nov-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Apr-2016
Programme Priority
5

Documentation