Report for Oct 2019
- Report Date
- October 2019
Achievements this period
- limited activity while focus on HR Strategic reporting
- early discussion on identifying Project Sponsor , Senior User and other key stakeholders
Issues
- Need to agree Project Sponsor / get Senior User from the University Strategic reporting community - potential capacity issue for key people - as these same people are already fully committed to SEP core systems and Finance Transformation work
- Planning delayed / End of Planning milestone will move back several weeksÂ
Next Steps
- Start Planning
- Start user engagement and start gathering use stories
- Set up Agile tools - JIRA Board , start creating Backlog of User stories
- Agree MVP ( Minimum Viable Product) , and agree priority areas within the large scope of Finance Strategic Reporting
- Approved budget
- 300.0 days
- Activity this month
- 0.4 days
- Activity this year
- 0.4 days
- Activity to date
- 0.4 days
- Estimate to complete current year
- 370.0 days
- Estimate to complete future years
- 0.0 days