Report for Oct 2019
- Report Date
- October 2019
Achievements this period
- End of Planning completed
- Sprint 4 completed - Tidy up EDW Setup activities, Finish off Estates UAT re-work ,Continue refining HR model and data
- Sprint 5 started - HR - Access layer prototype , Estates UAT re-work
- Git / Bamboo - scripts completed , ready for deployment to DEV and TEST, once Synch has been done from Source to Staging to Foundation
Issues
- Project team spent additional effort on EST109 Estates UAT - agreed to progress with this work up to 5 + 15 = 15 days effort to get EST109 deployed to LIVE
- Need to agree long term solution for managing connections to EDW from BI tools before the HR Datamart can be made available to a larger community of users / testers
Next Steps
- Full backlog to be collected for the HR datamart
- Complete Sprint 5
- Plan Sprint 6 / Alpha release
- Approved budget
- 300.0 days
- Activity this month
- 53.0 days
- Activity this year
- 164.0 days
- Activity to date
- 245.0 days
- Estimate to complete current year
- 374.0 days
- Estimate to complete future years
- 0.0 days