w/c 15th July 2019
w/c 15th July 2019
Closure activity continued
This article was published on
Jul 29, 2019
Project Info
Project
ETL Implementation
Code
DTI005
Programme
Digital Transformation - Enterprise Data Warehouse
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Bill Lee
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
02-Apr-2018
Planning Date
26-Oct-2018
Delivery Date
17-May-2019
Close Date
26-Jul-2019
Programme Priority
1
Overall Priority
Higher
Category
Discretionary
More project information
Documentation
Initiate
No documents
Plan
Project Brief
Execute
Implementation Plan
Deployment Checklist
Deliver
No documents
Close
Closure Report
Other
No documents