Impact

Priority and Funding

This is proposed as a High priority project, funded as part of the EDW programme, within the Digital Transformation initiative. This Project was originally kicked off in 17/18 and has suffered from a few delays due to recruiting external resource, therefore there has been some previous spend in 17/18. A summary of those figures as well as the initial estimates for delivery are as follows:

Spend to date

IS Internal Resource (17/18):       18 days (£5,760)

External Spend (17/18):                 £10,670

Total spend 17/18:                           £16,430

 

Initial Estimates

IS Internal Resource (18/19):       71.5 days (£25,025)

External spend (18/19):                 £19K

Total:                                                     £44,025

 

Total Costings

IS Internal Resource:                      89.5 days (£30,785)

External spend:                                 £29,670

Total:                                                     £60,455

 

Impact and Dependencies

This project need to deliver in order for the programme to reach the ‘Enterprise Ready’ milestone. 

 

Project Risks

Risk Description

Impact - Code and Description

Probability - Code and Description)

Risk Owner

Risk Management Approach

Mitigation Actions

Contingency Actions

There is a risk that IS staff will not be available or able to be committed to the project in the timescales required for implementation (by end August).

Moderate

Medium

Iain Fiddes

Retain

Ensure stakeholders & RMs bought into delivery plan.

Propose project as higher or highest priority to ensure resource focus. 

Ensure supplier able to take on wider implementation tasks.

There is a risk that project staff will leave the University or be redeployed to other projects in the course of the execution of this project.

Moderate

Medium

Iain Fiddes

Retain

Ensure stakeholders & RMs & line managers bought into delivery plan.

Ensure deputy resource identified and structured handover plans agreed.

There is a risk that UoE staff will not be able to provide sufficiently detailed information to Datalytix team to enable sizing and configuration of the proposed environments to be delivered.

Moderate

Low

Iain Fiddes

Reduce

Involvement of all internal parties in initial workshops.

Reliance on supplier expertise and guidance.

There is a risk that the Development team’s development, test and deployment processes are not defined in a way that enables the system to be configured and used in a way that maximises benefit.

Moderate

Low

Iain Fiddes

Reduce

Involvement of all internal parties in initial workshops.

Reliance on supplier expertise and guidance.

There is a risk that the provision identified within the DTI/EDW Programme budget for this project will be insufficient for delivery once detailed planning has been undertaken. 

Moderate

Medium

Chris Lawford

Reduce

Identify means of provisioning sufficient resource in 2018/19.

 

There is a risk that the timelines for delivery will not be met, either through materialisation of budget or staffing risks, or through technical issues.

Moderate

Medium

Alex Carter

Reduce

Address risks above.

Continue to use free-to-download Talend product in interim.

Assumption: Planning of project is based upon the the hybrid cloud architecture model.

If another architecture is chosen this will have an impact on the project plan, timescales and estimates.  

 

 

 

 

 

 

 

 

 

 

 

 

 

Implementation partner has limited experience in the hybrid cloud model.

 

 

 

 

Ensure involvement of Talend customer success architects.

 

UofE does not have experience of working with the chosen implementation partner. 

 

 

 

 

Establish formal governance, to include Talend.

Regular weekly PM meetings.

 

Talend Hybrid cloud solution doesn’t support Talend MDM (Master Data Mgmt) and ESB (Enterprise Service Bus) components.

 

 

 

 

 

 

 

Project Info

Project
ETL Implementation
Code
DTI005
Programme
Digital Transformation - Enterprise Data Warehouse
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Bill Lee
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
02-Apr-2018
Planning Date
26-Oct-2018
Delivery Date
17-May-2019
Close Date
26-Jul-2019
Programme Priority
1
Overall Priority
Higher
Category
Discretionary