Achievements
- Outstanding queries on workflow map identified and resolved, and updates made to the workflow maps.
- First draft of final project report (detailing future projects/work packages to be delivered and how they should be prioritized) created.
- Initial investigation conducted into work required to use students personal emails instead of creating a UoE email address.
Next Steps
- Final project report reviews completed (with wider project team and senior stakeholders) and report finalized.
- Planning and scoping of further projects.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days