Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2019 BLUE 0.0 days 0.0 days 0.0

Project Info

Project
DLAS Pilot Templates and Workflow Design
Code
DLAS002
Programme
Distance Learning at Scale (DLAS)
Management Office
ISG PMO
Project Manager
David Thresher
Project Sponsor
Jon Jack
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
02-Apr-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Jun-2019
Overall Priority
Normal
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.