Report for September 2019

Report Date
August 2019
Status

Planning, project brief, TAD, and initial risk assessment completed.

Staff comms have gone out. 4 sensors have been deployed and data is being collected, but not yet shared.  

Next Steps:
  • Planning to complete remaining deliverables (no date set for this:)
    • Deploy remaining sensors
    • CO2 level indicator lights in place on the floors.
    • Sharing of data with Facilities and H&S teams.
    • Decision regarding on-going deployment of solution, including agreed authorised users lists, and process for managing access going forward
Notes:
  • As planning for remaining activities has not completed, the current project delivery completion date of 20th Dec, and project closure date of 31st Jan are estimates.

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Argyle House CO2 monitoring
Code
DAT001
Programme
Data Technology Programme
Management Office
ISG PMO
Project Manager
Stephen Taylor
Project Sponsor
Simon Chapple
Current Stage
Plan
Status
In Progress
Project Classification
Transform
Start Date
07-Oct-2019
Planning Date
25-Oct-2019
Delivery Date
19-Jun-2020
Close Date
03-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation