Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for November 2019 November 2019 GREEN GREEN GREEN GREEN No Change
Report for October 2019 October 2019 GREEN GREEN GREEN GREEN No Change
Report for September 2019 August 2019 GREEN GREEN GREEN GREEN No Change

Project Info

Project
Argyle House CO2 monitoring
Code
DAT001
Programme
Data Technology Programme
Management Office
ISG PMO
Project Manager
Stephen Taylor
Project Sponsor
Simon Chapple
Current Stage
Plan
Status
In Progress
Project Classification
Transform
Start Date
07-Oct-2019
Planning Date
25-Oct-2019
Delivery Date
19-Jun-2020
Close Date
03-Jul-2020
Overall Priority
Normal
Category
Discretionary