Weekly update w/c 20/07/2015 |
- Latest version of RETAIN deployed to Live on Tuesday morning, including the implementation of the healthchecks on the live servers
- A last-minute bug was identified prior to go-live but Health&Safety agreed that the go-live should go-ahead and the issues could be investigated post-deployment
- Data refresh done on Test so that final UAT of outstanding issue can be undertaken on realistic data
- Closure meeting held with key stakeholders from Health & Safety and IS Applications
|
Dawn Holmes |
21-Jul-2015 |
|
Weekly update w/c 27/07/2015 |
- Final outstanding issues signed-off in Test and deployed to Live
- Final version of completion report distributed
- Project submitted for closure
|
Dawn Holmes |
31-Jul-2015 |
|
Weekly update w/c 06/07/2015 |
- Developer back from annual leave and back on project
- Development work taking place on outstanding issues which are preventing the go-live
- Maintenance sign-off booked for next week
|
Dawn Holmes |
10-Jul-2015 |
|
Weekly update w/c 01/06/2015 |
- Resource conflict for the BI Developer from FIN086. Revised timelines agreed so that both projects can progress
-
|
Dawn Holmes |
05-Jun-2015 |
|
Weekly update w/c 18/05/2015 |
- Further development & testing of User Stories as part of iteration 5
- Team meeting to evaluate required changes to the radioactivity reports. Further User Stories have been added to the backlog for this
|
Dawn Holmes |
22-May-2015 |
|
Weekly update w/c 11/05/2015 |
- No activities have taken place this week as one developer is on annual leave and the other is working on another project. Activities will resume as normal next week.
|
Dawn Holmes |
15-May-2015 |
|
Weekly update w/c 04/05/2015 |
- Iteration 4 completed this week. Details of the functionality delivered is documented on the iteration 4 page on the lefthand menu (direct link to iteration 4 page)
- Iteration 5 started this week with Health & Safety reps selected priority stories for development. Details of the stories selected can be found on the iteration 5 page on the lefthand menu (direct link to iteration 5 page)
|
Dawn Holmes |
15-May-2015 |
|
Weekly update w/c 27/04/15 |
- Development work is continuing on iteration 1.4 which is concentrating on the priority radioactivity user stories
|
Dawn Holmes |
01-May-2015 |
|
Weekly update w/c 20/04/15 |
- Iteration 3 completed this week and the iteration review meeting took place with key stakeholders. Key point of the meeting are noted on the iteration 1.3 page
- Iteration 4 started this week and the planning meeting took place with key stakeholders. User Stories were prioritised and selected for development alongside work carried forward from the previous iteration. This iteration will focus on radioactivity requirements.
|
Dawn Holmes |
24-Apr-2015 |
|
Weekly update w/c 13/04/15 |
- Development work is continuing on iteration 1.3
- Meeting held with H&S to examine options for addressing requirements for radiation recording by activity. Agreed to produce screen mock-ups to demonstrate preferred/simplest approach.
- Screen mock-ups for radiation recording by activity produced & supplied to H&S for review
|
Dawn Holmes |
17-Apr-2015 |
|
Weekly update w/c 30/03/2015 |
- User Story development ongoing for iteration 1.2
- Patching on the servers by Tech Management meant that the Dev & Beta systems were unavailable, but the developers were able to work locally to minimise the impact
- One of the developers was on 2 days leave which has reduced velocity this week
- Meeting held with H&S to discuss radioactivity enhancements for consideration in following iterations
|
Dawn Holmes |
02-Apr-2015 |
|
Weekly update w/c 23/03/2015 |
- Iteration 1.1 completed this week and the iteration review meeting took place with key stakeholders. Key point of the meeting are noted on the iteration 1 page
- Iteration 1.2 started this week and the planning meeting took place with key stakeholders. User Stories were prioritised and selected for development alongside work carried forward from the previous iteration. Selected stores are noted on the iteration 2 page
|
Dawn Holmes |
27-Mar-2015 |
|
Weekly update w/c 16/03/15 |
- Development of User Stories for Iteration 1.1 is ongoing as per plan
- Issues being encountered with auto-deployment which is delaying QA
- Both developers are being resource conflicted for Mon/Tue next week but this is not expected to affect the overall plan
|
Dawn Holmes |
19-Mar-2015 |
|
Weekly update w/c 09/03/15 |
- Further estimation meeting held to allocate story points tothe 'must have' User Stories
- Interation 1 planning meeting held & User Stories selected for first round of development (details at https://www.projects.ed.ac.uk/project/csg005/page)
- Development for iteration 1 started
- CF10 migration complete & TAD updated and distributed to support teams
- CF9 version of application disabled
- Multiple conflicts received for the developers from other projects (SCE004, STU236, TTU007 & RMAS). Discussions are ongo
|
Dawn Holmes |
13-Mar-2015 |
|
Weekly update w/c 02/03/2015 |
- User Stories gather at the Bio User Group have been consolidated and recorded in Jira Agile
- Meeting held with Product Owner and Bio Rep to agree product vision (see https://www.projects.ed.ac.uk/project/csg005/overview) and to prioritise the User Stories
- End of Foundations meeting held with all key project reps. The stage was signed off with a few provisos that need actioning prior to development starting next Tuesday
- First estimation meeting held. Further meetings are needed to complete all User Stories
|
Dawn Holmes |
06-Mar-2015 |
|
Weekly update w/c 23/02/2015 |
- User Group held with representatives from a cross-section of Schools to gather requirements for hte bio-hazard elements of the system
- User Stories documented and distributed for review by the User Group
- The Business Lead (Radioactivity-related requirements) has now left on early paternity leave. This was previously captured in the risk log so the team has a contingency plan to start work on the bio User Stories and the leave the radioactivity requirements until later iterations when the Business Lead will be back at work
- The technical work on the Coldfusion mig
|
Dawn Holmes |
27-Feb-2015 |
|
Weekly update w/c 16/02/2015 |
- End of planng stage formally signed off by project stakeholders and WIS
- Team meeting to agree and assign priority actions for CF9 to CF10 migration
- Presentation prepared for bio user workshop next week
|
Dawn Holmes |
20-Feb-2015 |
|
Weekly update w/c 09/02/2015 |
- Project Brief completed and circulated for review
- Meeting held with Health & Safety to review Project Brief, timeline, risks and progress with actions
- Bio User Group booked for 24th Feb
- Meeting held with Production Management and Dev Tech to discuss their involvement in the project
- All routine meetings now booked into diaries
|
Dawn Holmes |
13-Feb-2015 |
|
Weekly update w/c 02/02/2015 |
- Planning meeting held with Software Development to review scope, risks and general approach
- First draft of Project Brief in progress
|
Dawn Holmes |
05-Feb-2015 |
|
Weekly update w/c 26/01/2015 |
- Project Manager allocated
- Project website created
- Kick-off meeting held with Project Sponsor and key business stakeholders to discuss project scope, timescales and stakeholders
|
Dawn Holmes |
04-Feb-2015 |