Title Report Date Time Cost Scope Overall Change
Report for December 2019 December 2019 AMBER GREEN AMBER AMBER No Change
Report for November 2019 November 2019 AMBER AMBER AMBER No Change

Project Info

Project
Core Systems - Systems Integration
Code
COR005
Programme
Service Excellence - Core Systems (SEPCOR)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Jennifer Milne
Current Stage
Plan
Status
In Progress
Project Classification
Transform
Start Date
04-Nov-2019
Planning Date
12-Dec-2019
Delivery Date
28-Nov-2020
Close Date
17-Dec-2020
Programme Priority
1
Overall Priority
Highest
Category
Discretionary