Organisation
Work/Task Breakdown
Agreement has been reached with all IS APPS resource managers that the high level plan and workload is acceptable for their teams.
Initiate / Plan
Brief - Project Services - All
Grouper Version Review - Development Team
Determine Scope of known Error Inclusion - all
High Level Design - Development Team
Review Design
Create Plan - Project Services
Detailed Design - IS APPS, Service Management
Execute
Phase 1 - Push
Management - Project Services
SOA Environments - Dev Tech
Design - Development Team
Develop - Development Team
Peer Test - Development Team
Deploy - Dev Tech
TEST - Service Management / User Groups
Deploy to LIVE - Tech Man/AppMan
Phase 2 - Inbound
Management - Project Services
SOA Environments - Dev Tech
Design - Development Team
Develop - Development Team
Peer Test - Development Team
Deploy - Dev Tech
TEST - Service Management / User Groups
Deploy to LIVE - Tech Man/AppMan
Phase 3 - Pull
Management - Project Services
SOA Environments - Dev Tech
Design - Development Team
Develop - Development Team
Peer Test - Development Team
Deploy - Dev Tech
TEST - Service Management / User Groups
Deploy to LIVE - Tech Man/AppMan
Phase 4 - Grouper
Management - Project Services
Environments - Dev Tech/ITI
Design - Development Team
Develop - Development Team
Peer Test - Development Team
Deploy - ITI
TEST - Service Management / User Groups
Deploy to LIVE - ITI
Close/Review
Closure - All
Resources Skills and Cost
The breakdown of resources for the project will be as follows :-
IS Apps Project Services - 61 days IS Apps Dev Team - 183 days IS Apps Dev Tech - 46 days IS Apps Prod App Man - 19 days IS Apps Prod Tech Man - 9.5 days IS ITI - 8.5 days IS Apps Serv Mgt: - 130 Days