Status Report for July 2019
- Report Date
- July 2019
Summary
Programme Board now in transition to CIS014 (Deployment Project). Lessons learned meeting expected to take place mid-August followed by formal project closure.
Achievements in Last Period
- final Programme Board meeting
Issues and Risks
- see risk register
Next Steps
- lessons learned
- project closure
Future Milestones
Stage | Milestone | Due Date |
---|---|---|
Close | Close | 30-Aug-19 |
- Approved budget
- 738.0 days
- Activity this month
- 2.0 days
- Activity this year
- 993.5 days
- Activity to date
- 1093.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days