Status Report for June 2019

Report Date
June 2019

Summary

Board meeting approved requirements prioritisation.  Contracts signed by UoE 13th June, returned (signed) on 26th June.

Achievements in Last Period

  • formal contract signature

Issues and Risks

 

Next Steps

  • lessons learned
  • final Programme Board meeting
  • project closure

 

Future Milestones

Stage Milestone Due Date
Close Close 30-Aug-19

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
738.0 days
Activity this month
18.0 days
Activity this year
991.5 days
Activity to date
1091.0 days
Estimate to complete current year
7.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Network Replacement Procurement
Code
CIS009
Programme
ITI - Communications Infrastructure (CIS)
Management Office
ISG PMO
Project Manager
Karen Wilson
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
31-May-2017
Planning Date
29-Sep-2017
Delivery Date
26-Jun-2019
Close Date
02-Oct-2019
Overall Priority
Highest
Category
Compliance

Documentation