Status Report for June 2019
- Report Date
- June 2019
Summary
Board meeting approved requirements prioritisation. Contracts signed by UoE 13th June, returned (signed) on 26th June.
Achievements in Last Period
- formal contract signature
Issues and Risks
- see risk register
Next Steps
- lessons learned
- final Programme Board meeting
- project closure
Future Milestones
Stage | Milestone | Due Date |
---|---|---|
Close | Close | 30-Aug-19 |
- Approved budget
- 738.0 days
- Activity this month
- 18.0 days
- Activity this year
- 991.5 days
- Activity to date
- 1091.0 days
- Estimate to complete current year
- 7.0 days
- Estimate to complete future years
- 0.0 days