Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2019 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
George Square, 50, L2&3, AV Upgrade 2020
Code
AV2849
Programme
ISG Learning and Teaching Spaces (LTS)
Management Office
ISG PMO
Project Manager
David Whitaker
Project Sponsor
Euan Murray
Current Stage
Plan
Status
In Progress
Project Classification
Run
Start Date
01-Oct-2019
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Sep-2020
Overall Priority
Normal
Category
Compliance

Documentation

Not available.

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.