Monthly Report

Report Date
September 2018
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
We have an issue with being able to procure AV contractors currently. The APUC agreement has lapsed and the new one is not in place. Hopefully, it will start in the next few weeks. However, we need to procure this now to hit the Semester 2 completion date. Currently trying to get Procurement and Estates to make a decision.
Change Status
Time
Significant
Cost
No Change
Scope
No Change
Overall
Significant
Has formal escalation taken place?
No
Change Commentary
See RAG commentary.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ECA - Main Lecture Theatre
Code
AV2726
Programme
ISG Learning and Teaching Spaces: CAHSS (AV)
Management Office
ISG PMO
Project Manager
Stephen Carter
Project Sponsor
Geoffrey Lee
Current Stage
Close
Status
Closed
Start Date
01-Oct-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Jan-2019
Overall Priority
Normal
Category
Compliance

Documentation