w/c 20th January 2020

  • Core Finance System Integration 
    • Enquiries made to SEP regarding internal catering procurement processes and feedback received regarding aligning internal to external procurement processes
    • Further thoughts received potential integration options in relation to the Core Finance system  
  • Potential Suppliers
    • feedback received from two of the suppliers and circulated to the project team 
  • Procurement Question Sets
    • Feedback from the Development team regarding the question set 

Project Info

Project
Delivered Catering Procurement
Code
ACS042
Programme
Accommodation Catering and Events (ACE)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Ian Macaulay
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
30-Aug-2019
Planning Date
20-Sep-2019
Delivery Date
14-Feb-2020
Close Date
28-Feb-2020
Programme Priority
1
Overall Priority
Normal
Category
Discretionary