December 2014
- Report Date
- December 2014
Report compiled by Maurice Franceschi, (IS Apps Programme Manager) for Mark Wetton and Anne-Marie Scott
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: AMBER
The programme has a large number of ('Apps') projects reflecting the activity and expectations being generated in the TEL area. Amongst its challenges and opportunites, there is the new LTW division and changes in the way of working and relationships with rest of IS which that will bring. So an exciting time.
Programme Manager sets the status of programme as Amber given the uncertainty around the Clickers Procurement award of contract and possible risk to that project and also implementation of the solution in time for 2015/16 start of term. Other project prograssing well and budget fine.
Annual Planning is well under way and proposals prepared and prioritised. The first draft of the 'Red Line' show a good outcome for TEL.
IS Applications Projects

USD Projects
Planning not in place.
IS Applications Budget

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary |
| Working with APPS | |
| Moodle Upgrade | Planned annual upgrade of Moodle VLE platform. We should be looking at a yearly upgrade but jumping 2 versions at a time (upgrading in June/July each year). The exact version each year will be dependent on our plugins and how quickly they can be tested/redeveloped by non-Moodle HQ developers. At present we expect to deploy in July the version that comes out in the December previous |
| Online Assesment Evaluations | The development of pilot projects exploring the use of technologies and functionality for innovative assessment and feedback practice. Focus will be on evaluating opportunities and challenges for integration with existing systems, best match with pedagogic requirements, adaptability and scalability. We anticipate that the technologies explored will be a mix of hosted (cloud-based) and installed here. Schools and courses with a history of innovative approaches to assessment will be identified and invited to develop these pilots. Three separate projects are expected :- Adaptive Learing - Started as TEL014 Map My Programme Feedback Analytics Capture Systems |
| TELS Management Information | This project will deliver a management information reporting solution that Schools and IS can use to understand the breadth and depth of engagement with IS Technology Enhanced Learning Services. It will be possible to see the picture at individual School level, at College level, or for the institution as a whole. |
| LTW Projects | |
| VLE STudent Analytics - Moodle | TEL019 |
| ePortfolio Gap Analysis | |
| TAG Assessment Tools | |
| TREE | TEL020 |
| Also note there are two other projects of interest to TEL | Multimedia Procurement and Multilemedia Implementation - Major Proejcts being delivered by the separate Multimedia Programme, but which will be services supported by TEL once delivered. |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||
Next Generation Personal Response System (PRS) - ProcurementCompliance
Milestones new milestones rejected by WIS. PM to go back to Sponsor.
RAG Status RED | Report by Maurice Franceschi for December 2014The assessment proces is now completed. After discussions with project sponsor on the project team recommendation, status is RED. Talk to PM for further details. An additional 5 days to be transferred to the project to fund ongoing (mostly PM) post-assessment activity and for T&C's.
| ||||||||||||||||||||||||||||
Learn Automated Failover Milestones
RAG Status GREEN | Report by Colin Forrest for December 2014
Achievements in the last period
Issues
Next Steps
| ||||||||||||||||||||||||||||
Online Assessment/Feedback Evaluations - Adaptive Learning
Milestones:
RAG Status GREEN
| Report by Sue Woodger for December 2014Achievements
Issues
Next Steps
| ||||||||||||||||||||||||||||
VLE Student Analytics Milestones
RAG Status GREEN
| Achievements this period Achievements this period
Issues
Next Steps
| ||||||||||||||||||||||||||||
QMP Upgrade Milestones:
******Note - Milestones are now being reworked to aim for Innovative Learning week. This has been confirmed in a morning meeting with the Project Team but there was not enough time to formally change the Milestones before the deadline for these reports.
RAG Status GREEN | Report by Colin Forrest for December 2014Achievements in the last period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
| No projects closed |