MVM Programme Report for Portfolio Owner Paul Clark
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
The MVM programme started 2015/16 at a significant time for MVM, with the emergence of a long term road map for its IT Strategy.
All projects that are expected to be part of this year's programme of work, including projects not involving Applications (see College Led programme), have been added to the projects website. Only projects needing Applications resource will be added here.


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
| All projects in progress. However, in-year projects are expected - see the MVM Portfolio planning summary for list of projects and small pieces.
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||
MVM LTS service transition to IS Category: Funded
Milestones
RAG Status GREEN | Report completed by Maurice Franceschi for February 2016
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
Anatomy Museum Application Category: Core Funded
Milestones
RAG Status GREEN | Report completed by Maurice Franceschi for February 2016
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
|
MVM005 (AP45-905) Simulated Patients Enhancements Category: Funded
Milestones
RAG Status RED
| Report completed by Maurice Franceschi for Dave Berry for February 2016
Programme Manager Maurice Franceschi and Head of Applications Development Iain Fiddes met with key stakeholders, including Project Sponsor Keith Wylde, Business Lead Bryan Allen, user Trisha Lamb and (ex) MVM technical support staff Gary Blackie and Alan Gilchrist. Together, we
The recommendation from Programme Manager and Applications Development Section Head to the business, was that the application was not fit for purpose and that there was no benefit to stakeholders in continuing with further remedial action and development, and that accordingly the project should be closed. Project Sponsor Keith Wylde accepted the recommendation. Programme Owner Paul Clark also fully supports the recommendation and decision taken. A closure report from project manager Dave Berry may take some time to write up, due to his other priorities and the issues that may have to be recorded as part of the project, and the need to sign off the report with the stakeholders.
The UAT was not successful: new issues were reported. There is no budget remaining to address the issues. This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/16 As noted for the last two months: - Synchronisation with Outlook is failing on the business's new PCs. The PM and developer have recommended that the MVM CO's investigate this problem. This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/14 - The business have requested further changes but there is no agreement in place for funding further work. This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/13.
- Write closure report and close project by 31st March RAG status set to RED because the project has overspent and not delivered.
| ||||||||||||||||
| MVM007 (AP45-905) NHS Data Share - Process Mapping Category: Core Funding
Milestones
RAG Status GREEN | Report completed by Maurice Franceschi for February 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
| MVM009 (AP56-905) Tristan Replacement Category: Funded
Milestones (to be reviewed with Project Board when ITT published)
RAG Status AMBER | Report completed by Colin Watt for February 2016Achievements in Last Period
Issues
Next Steps
The project current status is AMBER due to additional delay on timeline. | ||||||||||||||||
MVM010 (AP56-033) CMVM and LTW Lecture Capture Pilot Category: Discretionary
Milestones To be confirmed during planning.
RAG Status AMBER | No report for February.
Project stays at Amber.
| ||||||||||||||||
MVM012 (AP56-033) Review of the Speedwell service Category: Discretionary Milestones
RAG Status AMBER | Report completed by David Watters for February 2016Achievements this Period
Issues
Next Steps
Project is Amber due to illness and also further scope has been added to the project needing new milestone for closure which is now past. |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
| Project was closed on 04/08/15 MVM006 Completion Report |