MVM Programme Report for Portfolio Owner Paul Clark

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update  

Overall Programme RAG: GREEN

The MVM programme started 2015/16 at a significant time for MVM, with the emergence of a long term road map for its IT Strategy.

All projects that are expected to be part of this year's programme of work, including projects not involving Applications (see College Led programme), have been added to the projects website. Only projects needing Applications resource will be added here.

Projects all on track, with just MVM007 needing new milestones now that its scope has been changed. MVM005 also needing resolved.

 

 

 

 

 

 

 

Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary

 

 

All projects in progress. However, in-year projects are expected - see the MVM Portfolio planning summary for list of projects and small pieces.

 

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

MVM002(AP34-922)

MVM LTS service transition to IS

Category: Funded

 

Milestones

15-Feb-2016Confirm that High Robson can be cleared
22-Feb-2016Decommissioning of machine room servers completed
29-Feb-2016Closure

 

RAG Status

GREEN

Report completed by Maurice Franceschi for January 2016

 

Achievements in Last Period

  • complete the migration of  windows simple hosting to Plesk - not moved to Plesk, but migrated.
  • move MVM Room Booking to Plesk - not moved to Plesk, but migrated.

Issues

  • no open issues
  • no medium or high risks

Next Steps

  • switch off all servers in High Robson

  • Wait two weeks to ensure nothing has been missed
  • Request ITI to arrange decommissioning
  • Close project
 

 

MVM004 (AP45-080)

Anatomy Museum Application

Category: Core Funded

 

Milestones

12-Feb-2016Application User Acceptance Sign-Off
12-Feb-2016Payment Schedule 4 (20%)
22-Feb-2016Delivery of Application - submission to Apple
29-Feb-2016Closure

 

 

RAG Status

GREEN

Report completed by Maurice Franceschi for January 2016

 

Achievements in Last Period

  • start UAT - t achieved
  • complete UAT - first pass done - Luma working on fixes
  • publish application to public

Issues

  • no issues
  • no risks

 

Next Steps

  • complete UAT
  • publish application to public
  • close project
  •  

 

MVM005 (AP45-905)

Simulated Patients Enhancements

Category: Funded

 

Milestones

 

TBC

 

RAG Status

RED  

Report completed by Maurice Franceschi for Dave Berry for January 2016

  • Achievements in Last Period

 

  - Discuss options for further work - clarity on funding and way forward

  - Outcome of CO investigation of synchronisation problem.

The UAT was not successful: new issues were reported.  There is no budget remaining to address the issues.  This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/16

As noted for the last two months:

  - Synchronisation with Outlook is failing on the business's new PCs.  The PM and developer have recommended that the MVM CO's investigate this problem.  This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/14

  - The business have requested further changes but there is  no agreement in place for funding further work.    This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/13.

RAG status set to RED because the way forward needs to be agreed before budgets can be resolved and new milestones set.

Next Steps

 

  - Discuss options for further work - meeting being arranged for February

  - Await outcome of CO investigation of synchronisation problem - wil review in February

Issues

MVM007 (AP45-905)

NHS Data Share - Process Mapping

Category: Core Funding

 

Milestones

 

TBC  

RAG Status

RED

Report completed by Maurice Franceschi for January 2016

 

Achievements in Last Period

  • project pending action from Sponsor to find a new team to pilot the process and documents

Issues

  • no medium or high risks

Next Steps

  • replan with team once confirmed

Milestones

  • New milestones to be confirmed once the team piloting the processs and documents has confirmed their dates.

 

RAG Change Status is Red as the current milestones for acceptance and delivery needs to be replanned, as the project scope has changed to include a pilot of the process and documents. This is at the sponsor's request, helping to make the deliverables of highest quality. New milestones for acceptance and closure) to be confirmed once the team piloting the processs and documents has confirmed their dates. The project status will move back to Green after this.

Project has been waiting three month for this information. Project Manager wil advise suspending project if no pilot team is found, or descoping this.

 

MVM009 (AP56-905)

Tristan Replacement

Category: Funded

 

Milestones

(to be reviewed with Project Board when ITT published)

22-Jan-2016Issue Invitation To Tender (ITT)
04-Mar-2016Return of ITT
08-Mar-2016ITT Evaluation Starts
15-Apr-2016ITT Evaluation Phase Ends
18-Apr-2016Award Recommendation
29-Apr-2016Award Letter
13-Jun-2016Contract Signed
15-Jul-2016Closure
 

RAG Status

RED

Report completed by Colin Watt for January 2016

Achievements in Last Period

  • Work on simplification of ITT by request of the project board, particularly mandatories.
  • Workshops held early January with MVM staff to agree supplier demonstration scenarios.
  • Business Lead requested that scenarios be expanded to include detailed checklists to allow MVM staff to agree exactly what is required to step through each evaluation; this has been agreed with Procurement, Programme Manager and Senior Supplier, but will impact on completion and approval of ITT.
  • Work on ITT now planned for completion w/c 08/02/16.

 

Issues

  • Delay to timeline due to expansion of supplier demonstration scenarios. PM assisting Business Lead to complete revised scenarios and ITT.

 

Next Steps

  • Complete and issue ITT.
  • Produce revised plan for timeline including suoplier evaluations.
  • Agree contingency plans for current platform if procurement delayed.

The project current status is RED due to delay on timeline.

MVM010 (AP56-033)

CMVM and LTW Lecture Capture Pilot

Category: Discretionary

 

Milestones

To be confirmed during planning.

 

RAG Status

AMBER  

Report completed by Colin Forrest for January 2016

Achievements in the last period

  • As part of the planning we are completing the purchase list for all the rooms included in the pilot.  This has included contributions from HSS as well as Learning Technology Spaces.
  • The purchase list is now with the sponsor for sign off.  Getting this completed was our highest priority.
  • We have also agreed a process and order for our tasks and so we can complete the planning phase of the project within the next week.

Issues

  • Planning has not been completed yet, but we have been concentrating on our main priority which was to get the purchase list completed and signed off.  Several meetings have taken place to resolve this list.  I'm instructued that purchasing is the number one priority.
  • Obtaining a clear direction on suitable cameras for the appropriate rooms has not been straighforward.  We have a meeting with LST, HSS and the MVM Support team set for the 04th of Feb to flesh out the final details.  This delay in getting the accurate camera information is causing the Amber status.

Next Steps

  • Order the equipment.
  • Agree an installation plan.
  • Finalise planning

 

 

MVM012 (AP56-033)

Review of the Speedwell service

Category: Discretionary

Milestones

 

26-Feb-2016Project completion

 

RAG Status

GREEN

Report completed by David Watters for January 2016

Achievements this Period

  • Report written up and distributed to stakeholders

Issues

  • Completion of report has engendered need for more analysis

Next Steps

  • Report to be enhanced with further information sought by stakeholders
  • Project to be closed

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

MVM006

MVM Migration To EdWeb and Site Restructure

Project was closed on 04/08/15 MVM006 Completion Report