MVM Programme Report for Portfolio Owner Paul Clark

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update  

Overall Programme RAG: GREEN

The MVM programme started 2015/16 at a significant time for MVM, with the ermergence of a long term road map for its IT Strategy.

All projects that are expected to be part of this year's programme of work, including projects not involving Applications (see College Led programme), have been added to the projects website. Only projects needing Applications resource will be added here.

Although status is Amber / Red for several projects, this reflects changes in scope or small delays in delivery milestone, and all projects will be back to Green already or soon. Programme remains Green. Sponsor funded MVM005 remains the one project of concern, with budget spent and UAT still not completed and business want scope changes.

Project MVM010 Lecture Capture assessment projec thas just started.

 

 

 

 

 

 

 

Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary

 

 

All projects in progress. However, in-year projects are expected - see the MVM Portfolio planning summary for list of projects and small pieces.

 

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

MVM002(AP34-922)

MVM LTS service transition to IS

Category: Funded

 

Milestones

 

30-Oct-2015Adobe Connect moved to Applications for Support
06-Nov-2015Migration of Complex Applications Completed
20-Nov-2015Migrate Windows Simple Hosting (Phase II)
04-Dec-2015Decommissioning of machine room servers completed
11-Dec-2015Closure

 

 

RAG Status

AMBER  

Report completed by Maurice Franceschi for October 2015

 

Achievements in Last Period

  • migrate Complex Environments (eeMec, examinations, non-windows sites) - not complete, but only eeVec to migrate now
  • migrate windows simple hosting - not started
  • move adobe connect to upgraded infrastructure - not complete, but just waiting for users to confirm a downtime window

Issues

  • no open issues
  • no medium or high risks

Next Steps

  • migrate last Complex Environments (eeMec, examinations, non-windows sites) (Mid-October)
  • migrate windows simple hosting
  • move adobe connect to upgraded infrastructure

 

RAG Change Status is Amber - the project delivery has slipped back a couple of weeks, in the reporting period, as a couple of the migrations had to wait for later date in the month that suited college better. The project status is now Green.

 

 

MVM004 (AP45-080)

Anatomy Museum Application

Category: Core Funded

 

Milestones

19-Nov-2015Application User Acceptance Sign-Off
20-Nov-2015End of Build - Ready for UAT
04-Dec-2015Deployment Sign-Off
11-Dec-2015Closure
18-Dec-2015End of UAT
23-Dec-2015Delivery of Application - submission to Apple and Andriod Store
23-Dec-2015Payment Schedule 4 (20%)

 

RAG Status

RED  

Report completed by Maurice Franceschi for October 2015

 

As there is not enough time to do a full UAT before Prof. Findlater's lecture on 23/11, the team has agreed to stay with the prototype until the 23rd and start UAT after that.

 

Achievements in Last Period

  • deliver further content by end of October - done
  • deliver voice over recordings - done

Issues

  • no issues
  • no risks

 

Next Steps

  • complete build of prototype
  • demo prototype at Prof Findlater's Inaugral lecture on the 23rd
  • use prototype at main library exhbition warly December
  • start UAT
  • complete UAT (December)
  • submit app to Apple (Christmas)
  • delivery (Jan 2016)  

RAG Change Status is Red.  The delivery has moved back more than a month in the last reporting period, as disucssed and agreed with the project sponsor. The project status is now Green.  

MVM005 (AP45-905)

Simulated Patients Enhancements

Category: Funded

 

Milestones

02-Oct-2015Acceptance Sign-off
16-Oct-2015Closure
16-Oct-2015Deployment Sign-Off

 

RAG Status

RED  

Report completed by Dave Berry for October 2015

Achievements in Last Period

The PM and developer met with the business lead to review the issues raised during further UAT.  Bugs preventing correct operation of the current functionality were fixed and returned for further testing.

Issues

- Synchronisation with Outlook is failing on the business's new PCs.  The PM and developer have recommended that the MVM CO's investigate this problem.  This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/14

- The business lead has not been able to test the latest fixes in the agreed time and so the milestones will need to be revised.  This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/13, although the date noted in that issue has also been missed.

- The business have requested further changes but there is  no agreement in place for funding further work.    This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/13.

- The budget has been exceeded by a couple of days.

RAG status set to RED because milestones & budget need to be agreed, along with resolution of request for further work.

Next Steps 

- Await outcome of testing the latest fixes.

- Await outcome of CO investigation of synchronisation problem.

- Discuss options for further work.

 

MVM007 (AP45-905)

NHS Data Share - Process Mapping

Category: Core Funding

 

Milestones

 

TBC  

RAG Status

RED

Report completed by Maurice Franceschi for October 2015

 

The project has had its scope changed so that a pilot of the process and document set will be done within the project.

 

Achievements in Last Period

  • acceptance of single document set - not completed
  • publish the process map - not completed
  • publish the process checklist and document set - not completed

Issues

  • no medium or high risks

Next Steps

  • acceptance of single document set
  • publish the process map
  • publish the process checklist and document set  

RAG Change Status is Red as the current milestones for acceptance and delivery needs to be replanned, as the project scope has changed to include a pilot of the process and documents. This is at the spnsor's request, helping to make the deliverables of highest quality. It is likely that new dates will slip by more than a month - expecting confirmation from piloting team of dates by 9th Novm,ber.

New milestones for acceptance and closure) to be confirmed once the team piloting the processs and documents has confirmed their dates. The proect status will move back to Green by mid-November.

 

MVM009 (AP56-905)

Tristan Replacement

Category: Funded

 

Milestones

(to be confirmed with Project Board)

 

RAG Status

GREEN

Report completed by Colin Watt for October 2015

Achievements in Last Period

  • First pass of requirements for ITT reviewed with Project Sponsor / Business Lead.
  • Draft procurement strategy produced and reviewed with Project Sponsor / Business Lead.
  • Project Board convened for November.
  • PIN issued; questions sent to PIN respondents in order to set up potential visits prior to formal procurement.

 

Issues

  • No major issues.
  • Earliest opportunity for Project Board is Mid-November, so likely that end of planning will be delayed given that the board needs to agree project governance, budget, timeline and plan, however the team is proceeding with the requirements for the ITT on the basis that (with Board approval) this can be issued quickly following agreement on the above.
  • Funding, project resourcing, and timeline to be covered with Project Board.

 

Next Steps

  • Agree budget, timeline, plan with Project Board.
  • Agree procurement strategy.
  • Complete and issue ITT.  

MVM010 (AP56-033)

CMVM and LTW Lecture Capture Pilot

Category: Discretionary

 

Milestones

04-Dec-2015Planning sign-off

 

RAG Status

GREEN  

Report completed by Colin Forrest for October 2015

 

Programme Manager note :

Project has just initated. PM is on annual leave.

 

 

MVM012 (AP56-033)

Review of the Speedwell service

Category: Discretionary

Milestones

 

05-Nov-2015Planning sign-off
22-Jan-2016Delivery milestone
29-Jan-2016Project completion

 

RAG Status

GREEN

Report completed by David Watters for October 2015

Achievements this Period

  • Project initiation approved by WIS
  • Website established & project brief drafted

Issues

  • None

Next Steps

  • Project brief to be submitted to WIS
  • Consultations to commence with MVM staff

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

MVM006

MVM Migration To EdWeb and Site Restructure

Project was closed on 04/08/15 MVM006 Completion Report