September 2015
- Report Date
- September 2015
MVM Programme Report for Portfolio Owner Paul Clark
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
The MVM programme started 2015/16 at a significant time for MVM, with the ermergence of a long term road map for its IT Strategy. There are five projects carrying over into this year.
The Tristan Replacement - Procurement project has started.
All projects that are expected to be part of this year's programme of work, including project not involving Applications, have been added to the projects website. Only projects needing Applications resource will be added here, over time.

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
| All projects in progress. However, in-year projects are expected - see the MVM Portfolio and Programmes on the proejcts website.
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||
MVM LTS service transition to IS Category: Funded
Milestones
RAG Status GREEN | Report completed by Maurice Franceschi for September 2015
The migration of most the Complex Applications is expected to complete by 12th October. There is a dependnacy on OSCA migration for some sites - we'll see how this develops over the coming week. Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
Anatomy Museum Application Category: Core Funded
Milestones
RAG Status GREEN | Report completed by Maurice Franceschi for September 2015
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
| MVM005 (AP45-905) Simulated Patients Enhancements Category: Funded
Milestones
RAG Status Amber | Report completed by Maurice Franceschi for Dave Berry for September 2015
Achievements in Last PeriodNothing to report as the business were not able to test until the end of the month IssuesTesting raised further issues. These will be reviewed on Oct 7th. Next StepsDetermine what would be needed to resolve the issues. The project status is Amber because the issues may require more time and effort. The funding for any further work is unclear. | ||||||||||||||||
| MVM007 (AP45-905) NHS Data Share - Process Mapping Category: Core Funding
Milestones
RAG Status GREEN | Report completed by Maurice Franceschi for September 2015
Project has been increased in scope to also include drafting of document templates.Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
MVM009 (AP56-905) Tristan Replacement Category: Funded
Milestones (to be confirmed with Project Board)
RAG Status GREEN | Report completed by Colin Watt for September 2015 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
| Project was closed on 04/08/15 MVM006 Completion Report |