August 2015

Report Date
August 2015

MVM Programme Report for Portfolio Owner Paul Clark

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update  

Overall Programme RAG: GREEN

The MVM programme starts 2015/16 at a significant time for MVM, with the ermergence of a long term road map for its IT Strategy. We aim to participate in the IS three year annual planning with formal proposals.

There are five projects carrying over into this year.

The Tristan Replacement - Procurement project is about to start, which is a funded project is a key project for MVM.

All projects that are expected to be part of this year's programme of work, including project not involving Applications, have been added to the projects website. Only projects needing Applications resource will be added here, over time.  

 

 

 

 

Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary

 

 

All projects in progress. However, in-year projects are expected - see the MVM Portfolio and Programmes on the proejcts website.

 

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

MVM002(AP34-922)

MVM LTS service transition to IS

Category: Funded

 

Milestones

21-Aug-2015Migrations in TEST signed-off
28-Aug-2015Remove dependancy of Easter Bush vm host on the Hugh Robson infrastructure
28-Aug-2015Adobe Connect moved to Applications for Support
02-Oct-2015Migration of Complex Applications Completed
09-Oct-2015Migrate Windows Simple Hosting (Phase II)
13-Nov-2015Decommissioning of machine room servers completed
20-Nov-2015Closure

 

 

RAG Status

GREEN  

Report completed by Maurice Franceschi for August 2015

 

Achievements in Last Period

  • clear timetable to migrate complex  sites by ealy October
  • sign-off Complex Migrations in TEST - not completely - expected early Sept.
  • sign-off TAD and live environments - achieved
  • migrate Complex Environments - not achieved - new date set
  • agreement set on how Easter Bush vm host will be handled

Issues

  • the new windows servers from COM014 project available earlier than planned, so milestone brought forward to early October
  • no medium or high risks

Next Steps

  • sign-off Complex Migrations in TEST
  • migrate Complex Environments (October)

 

 

 

 

MVM004 (AP45-080)

Anatomy Museum Application

Category: Core Funded

 

Milestones

 

30-Oct-2015End of Build - Ready for UAT
19-Nov-2015Application User Acceptance Sign-Off
20-Nov-2015Delivery of Application - submission to Apple and Andriod Store
20-Nov-2015Payment Schedule 4 (20%)
04-Dec-2015Deployment Sign-Off
11-Dec-2015Closure

 

RAG Status

GREEN  

Report completed by Maurice Franceschi for August 2015

 

Achievements in Last Period

  • meeting to check on progress of content delivery - done - project replanned and new person to deliver content brought in
  • deliver content by September - in progress

Issues

  • no issues
  • risks - two amber risks

 

Next Steps

  • deliver content by September
MVM005 (AP45-905)

Simulated Patients Enhancements

Category: Funded

 

Milestones

18-Sep-2015Acceptance Sign-off
25-Aug-2015Closure
25-Aug-2015Deployment Sign-Off

 

RAG Status

GREEN

Report completed by Dave Berry for August 2015

 

Achievements in Last Period

All outstanding fixes were completed and the system was delivered to the business lead for final testing

Issues

The business lead has had to delay testing the system.

Next Steps 

If the tests prove the fixes satisfactory, the project will move to closure

MVM007 (AP45-905)

NHS Data Share - Process Mapping

Category: Core Funding

 

Milestones

 

02-Oct-2015Single Document Set - Accepted
23-Oct-2015Process Mapping - Checklist Accepted
30-Oct-2015Publish Process Checklist and Document Set
06-Nov-2015Closure

 

RAG Status

GREEN

Report completed by Maurice Franceschi for August 2015

 

Project has been increased in scope to also include drafting of document templates.

Achievements in Last Period

  • complete analysis - was done but further feedback means more requested

Issues

  • no medium or high risks

Next Steps

  • complete analysis
  • continue business analysis of Process Map
  • continue business analysis of  Documents

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

MVM006

MVM Migration To EdWeb and Site Restructure

Project was closed on 04/08/15 MVM006 Completion Report