Report for August 2018

Report Date
August 2018

IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf

 

 

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: GREEN

All projects planned, start dates set, continuing projects as planned or allocated budget for unplanned. Requests for project managers made.

 

Section Two: Projects Not Started  

Project Info Programme Manager's Commentary
   
(INF134) Logging Data Retention Start Date  Feb - PM Requested 23/8
(INF135) CF10 Upgrades Start Date  Oct - PM Requested 23/8
(INF136) Annual Business Technology End of Life Analysis Start Date  Jan - PM Requested 23/8
(INF137) Annual Infrastructure Rationalisation Decommissioning Start Date  Sep - PM Allocated
(INF138) Annual DR Review and Tests Start Date  Feb - PM Requested 23/8
(INF139) Annual Upgrade of Development Tools + frameworks Start Date  Sep - PM Requested 23/8
(INF140) Patching process for application components - Analysis Start Date  Oct - PM Requested 23/8
(INF141) Migration of VSS and SVN to GIT Start Date  Sep - PM Requested 23/8
(INF142) Move IS based Oracle databases to VMs and stretched cluster Start Date  Jan - PM Requested 23/8
(INF143) Database Environment upgrade proposal MYSQL Start Date  Oct - PM Requested 23/8
   

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

INF121 (17-18 project)

Migrate Core Databases to Oracle 12c

Milestones

14-Sep-2018 AppsDEV build sign off
05-Oct-2018 Test environment build for AppsTEST complete
26-Oct-2018 AppsTEST integration sign off
09-Nov-2018 AppsTEST Acceptance sign off
23-Nov-2018 Live environment build for AppsLive complete
04-Dec-2018 AppsLive deploy to LIVE
17-Dec-2018 AppsLive deployment sign off
25-Jan-2019 Closure

RAG Status

GREEN

 

Report by David Watters for August 2018

 

not available - David will provide update in September

INF127 (17-18 Project)

LAMP / WIMP Platform Upgrade

Milestones

Date Milestone
5-Oct-2018 Deploy Migrated Applications
12-Oct-2018 Deployment Review and Close

RAG Status

Green

Report by Anne Mathison for August 2018

Achievements :

  • Talks and Talks Reminder went live Aug 14th
  • WebPA completed in DEV
  • DRPS to be tested
  • DRPS went Live Aug 15th
  • WebPA completed in TEST and signed off ready to go live after the change freeze 30-Aug (23-Aug)
  • Closure to be started
  • Completed the last acceptance test of the other migrated applications (WebPA)
  • Delay to deploying WebPA the day before the change freeze

Issues

  • None

Next Steps :

  • Project milestones to be approved
  • Project TADs to be completed
  • WebPA to Go Live after the change freeze at the start of October
  • Decommission Lamp Servers in Dev, Test and Live  after WebPA is Live
  • Closure to be drafted ready for closure after WebPA is live

RAG Status of Green

 

 

INF129 (17-18 Project)

Database Resilience 17-18

Milestones              

  

31-Aug-2018 Phase 1- WIKi App Tier to metro stretch cluster - Delivery Complete
07-Sep-2018 Phase 1- - Closure
26-Oct-2018 Phase 2 - Stage 1 Database move to VM - Delivery Complete
14-Dec-2018 Phase 2 - Stage 2- Wiki Database to MSC - Delivery complete
21-Dec-2018 Project Close complete

                                                                             

RAG Status

 GREEN

 

 

 

Report by David Watters for August 2018

 

not available - David will provide update in September

 

 

   

 