- Report Date
- June 2018
IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf


Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
Programme remain on target to deliver and close projects in this year, although we have agreed that a couple will now deliver in 2018-19.
Section Two: Projects Not Started
Project Info |
Programme Manager's Commentary |
|
All projects started |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
INF121
Migrate Core Databases to Oracle 12c
Milestones
RAG Status / RAG change during last month
BLUE
|
Project Suspended until August
|
INF127
LAMP / WIMP Platform Upgrade
Milestones
RAG Status / RAG change during last month
Green
|
Report by Anne Mathison for June 2018
Achievements :
- HR Reward Calculator has been added to the Web-Proxy deployments
- HR Reward Calculator completed in DEV
- HR Reward Calculator completed and signed off in TEST
- Talks and Talks Reminder had bugs identified
- Talks and Talks Reminder has been fixed
- WebPA has been progressed
- The migrated remaining 3 WebProxy applications have been signed off in TEST
- Campus Maps, Tour Booking Apps, HR Reward Calculator
Issues
Next Steps :
- Six web-proxy Applications to Go Live on on July 3rd (Bamboo deployment -at risk only)
- July 3rd - PG Degree Finder had an issue, so all applications back to where they were
- Looking into issue with PG Degree Finder
- Unidesk calls to be created for
- DRPS, WebPA, and Talks and Talks Reminder
- Alerts to be created for
- DRPS, WebPA, and Talks and Talks Reminder
- Talks and Talks Reminder to be Tested
- Talks and Talks Reminder to be Signed off
- Talks and Talks Reminder to Go Live in July
- WebPA to be complete in DEV
- WebPA to be complete in TEST
- WebPA to be Tested
- WebPA to be Signed off
- WebPA to Go Live in July (2-Aug)
- DRPS to be set up in Live
- DRPS to Go Live 1-2-Aug
- Closure to be written
- Plan to complete project by 3-August
Rag Status of GREEN
|
INF128
Annual Infrastructure Rationalisation Decommissioning 17/18
Milestones
Project will close in July - delayed because of leave
RAG Status / RAG change during last month
Amber
|
Report by David Watters for June 2018
Achievements
- Individual servers decommissioned - more 2008 servers switched off & removed from network
- Migration of Grid database completed
- Project completion report drafted
Issues
- Unused effort returned to programme
Next steps
- Project closure to be completed
|
INF129
Database Resilience 17-18
Milestones
RAG Status / RAG change during last month
AMBER
|
Report by Maurice Franceschi for June 2018
Achievements This Period
-
Decision and timescale for Network Brocade fabric completion to allow replanning. - not achieved
-
Service Management team should be able to move the Wiki DEV and TEST back onto the Metro Stretch Cluster. - not achieved
-
Dev Tech resource assigned in July to work on Design for the metro stretch cluster for Databases
Issues
- RISK 15 - Issue with networks proved a 'blocker' for the application to move to LIVE. Network issues have resulted in the DEV and TEST environment being removed from the Cluster. Plan to move back when the issues are resolved.
Next Steps
-
Decision and timescale for Network Brocade fabric completion to allow replanning.
-
Service Management team should be able to move the Wiki DEV and TEST back onto the Metro Stretch Cluster.
-
Design document for stretched cluster for databases
-
New PM assgined
|
INF130
Annual DR Test and Review 17-18
Milestones
RAG Status / RAG change during last month
GREEN
|
Report by Craig Moore for June 2018
Achievements
- Requirements gathered and agreed by project team
- project brief approved by WIS
Issues
- No major issues at this time
Next Steps
- Monitor and control implementation of deliverables
|
Section Four: Closed or Withdrawn Projects
Project Info |
Project Managers Commentary |
INF123
16-17 Provisioning of Python environment
|
Closed |
INF126
Bamboo Recovery
|
Closed |
INF132
Application Monitoring Procurement
|
Withdrawn - no sponsor funding |