Report for September 2017

Report Date
September 2017

IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf

Section One: Programme Commentary, RAG and Resources Update

For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.

 

For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.

 

Section Two: Projects Not Started Section Three: Projects In Progress Section Four: Closed or Withdrawn Projects

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: AMBER

The programme status is set as GREEN but looking ahead to 17/18, we can anticipate needing significant additional funding required for the INF123 and INF126 projects which will not be available through the planned programme budget.

 

For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.

 

For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.

 

Section Two: Projects Not Started  

Project Info Programme Manager's Commentary
INF129 - INF (17-18) Database Resilience Planned to start October 2017, Priority 5
INF130 - INF (17-18) - Annual DR Review and Tests 17-18 Planned to start December 2017, Priority 6
INF131 - INF (17-18) - Annual Upgrade of Development Tools 17-18 Planned to start December 2017, Priority 7
INF132 - INF (17-18) Application Monitoring Procurement Discretionary project - funding to be confirmed by sponsor, Priority 9

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

INF121

Migrate Core Databases to Oracle 12c

Category: Compliance

 

Milestones

11-Aug-2017 GenTEST post migration (integration) sign off
25-Aug-2017 GenTEST Acceptance sign off
28-Aug-2017 GenLive deploy to LIVE
30-Aug-2017 DEV environment build for AppsDEV complete
06-Sep-2017 Re-estimation for AppsLive
11-Sep-2017 GenLive deployment sign off
15-Sep-2017 AppsDEV build sign off
22-Sep-2017 Test environment build for AppsTEST complete
18-Oct-2017 AppsTEST integration sign off
17-Nov-2017 AppsTEST Acceptance sign off
29-Nov-2017 Live environment build for AppsLive complete
06-Dec-2017 AppsLive deploy to LIVE
20-Dec-2017 AppsLive deployment sign off
19-Jan-2018 Closure

 

RAG Status / RAG change during last month

RED

Report by Chris Konczak for August 2017  

Achievements this Period

  • Post Dev migration testing complete with some issues found and mostly resolved.
  • Review of APPS migrations started, and start of environment build while waiting for testing to complete.

 

Issues

  • Milestones for remaining GEN will not be met and to be reviewed with the team.
  • Issues encountered with CALMAC and Insurance applications that require a security setting to be altered. An assessment will be carried out by Dev Tech on the security implication of lowering to this level and the risk will be reviewed at WIS.
  • Applications running on ColdFusion 10 and 11 are not supported or able to connect the Oracle 12.2 pluggable database. Development resource will review and the outcome will be reviewed at WIS
  • Extra budget is required as work is on-going with GEN in 17/18 which was anticipated to have been completed in 16/17.

 

Next Steps

  • Milestones to end of GEN to be planned
  • All issues to be resolved with GEN and migrate to TEST
  • Integration completed and UAT started

 

RAG Commentary

Setting project to RED

Issue. There are problems found with some application when testing GEN DEV post migration to DEV. These required development input which is resourced to investigate and resolve. Other problems were encountered that required time to diagnose and resolve and document for migration to TEST.

Project is RED due to milestones needing revised.

 

INF123

16-17 Provisioning of Python environment

Compliance

Milestones

Target Date

Title

29-Sep-2017

Closure

RAG Status

Green

Report by Chris Orrell for August 2017

Achievements in Last Period

  • DR testing completed successfully.
  • IDM Dashboard Migration completed and as the last deliverable the Delivery milestone has been marked complete.

Issues

Next Steps

  • Initiate project closure ready for 29 September.
  • Budget swap with HSS014 still to be completed.

RAG Commentary

Cost is rated amber only to reflect the fact a budget swap is still to be completed, which explains the 26 days unallocated.

 

INF126

Bamboo Recovery

Compliance

Milestones

Milestones will require review based on the outcome / decision made as per proposals submitted to the Project Sponsor / Information Security Team (ISSUE #2), meeting planned 08/09/2017.

18-Sep-2017 No date available End of encryption investigation
29-Sep-2017 01-Aug-2017 sign off complex updates
29-Sep-2017 01-Sep-2017 sign off MyED updates
02-Oct-2017 No date available Project closure

 

RAG Status

RED

 

Report by Richard Bailey for August 2017

 

Achievements in Last Period

  • Project currently suspended awaiting definition / direction from the Project Sponsor, at this stage no further passwords are to be reset
  • Project Proposals with associated estimates (See ISSUE #2 below) have been presented to the Project Sponsor and await direction / a decision

Issues and Risks

Next Steps

  • Re-plan / move the project forwards based on the outcome of the decision by the Project Sponsor, who is going to consult with the Chief Information Security Officer

RAG Commentary

ISSUE: The Project is currently suspended awaiting direction from the Project Sponsor once they have consulted with the Chief Information Security Officer Regardless of the outcome it is expected that both time and cost are going to increase and milestones will need to be re-agreed / set. Meeting arranged between Project Sponsor and Alistair Fenemore 08/09/2017.

INF127 (AP78-044)

LAMP / WIMP Platform Upgrade

Milestones

Date

Milestone
21-Sep-2017 Brief
30-Mar-2018 Deliver
13-Apr-2018 Close

RAG Status

GREEN

 

Report by Anne Mathison for August 2017

Achievements :

  • Project website INF127 created
  • First project kick off meeting held Mon 28-Aug
  • Decision to investigate contents of current Lamp/Wimp platform

Issues :

  • None

Next Steps :

  • Complete Brief
  • Brief signed off
  • Investigate contents of current Lamp/Wimp platform

INF128

Annual Infrastructure Rationalisation Decommissioning 17/18

Milestones

28-Sep-2017 Planning Sign-Off Plan
30-Mar-2018 Delivery milestone Deliver
13-Apr-2018 Project closure Close

 

RAG Status

Green

Report by David Watters for August 2017

Achievements

  • Project initiated and Project Manager identified as David Watters.
  • Initial consultations with business partners

Issues

  • None

Next steps

  • Finalisation of project brief, including estimate, plan and updated risk and stakeholder logs.
  • Actions that can be taken according to the plan as yet to be determined.

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary