Report for November 2017
- Report Date
- November 2017
IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: AMBER
The programme status is set as AMBER as we have significant unplanned resource for INF121 (in particular) and INF123,INF126 that removes our contingency completely.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
INF130 - INF (17-18) - Annual DR Review and Tests 17-18 | Planned to start December 2017, Priority 6 |
INF131 - INF (17-18) - Annual Upgrade of Development Tools 17-18 | Planned to start December 2017, Priority 7 |
INF132 - INF (17-18) Application Monitoring Procurement | Withdrawn November 2017 |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||
Migrate Core Databases to Oracle 12c Category: Compliance
Milestones
RAG Status / RAG change during last month RED |
Report by Chris Konczak for November 2017Achievements this Period
Issues
Next Steps
RAG CommentaryChange - Scope RED as change required to migrate NEWS from Oracle 12c to Oracle 12.2. Budget change required to complete GEN migration and additional NEWS 12.2 scope. Time red as a result of change of scope and the extra effort required for GEN migrations. Revised budget and plan has been approved by Programme Manager and Owner, and will be actioned w/c 11 December, no action from SMT required.
|
||||||||||||||||||||
INF127 (AP78-044) Milestones
RAG Status RED |
Report by Anne Mathison for November 2017Achievements :Platform progress
Issues
Next Steps :
RAG Commentary Change - Due to a resource conflict with the Unidesk Annual Upgrade project (SMI018), the milestones have been replanned and agreed with the Project Sponsor and Programme Manager. The project is now planned to deliver the new infrastructure in April 2018 (was previously January 2018). |
||||||||||||||||||||
INF128 Annual Infrastructure Rationalisation Decommissioning 17/18 Milestones
RAG Status Green |
Report by David Watters for November 2017Achievements
Issues
Next steps
|
||||||||||||||||||||
INF129 Database Resilience 17-18
Milestones
RAG Status AMBER
|
Report by Megan Graham for November 2017Achievements This Period
Next Steps
|
||||||||||||||||||||
INF133 Milestones To be agreed at WIS 03/11/2017
RAG Status GREEN |
Report by Richard Bailey for November 2017Achievements this Period
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
INF123 16-17 Provisioning of Python environment |
|
INF126 Bamboo Recovery |
Attachment | Size |
---|---|
![]() | 248.97 KB |
![]() | 227.45 KB |
![]() | 100.44 KB |
![]() | 190.87 KB |