Report for August 2017
- Report Date
- August 2017
IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf
Section One: Programme Commentary, RAG and Resources Update
For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.
For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.
Section Two: Projects Not Started Section Three: Projects In Progress Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: AMBER
The programme status is set as GREEN but looking ahead to 17/18, we can anticipate needing significant additional funding required for the INF123 and INF126 projects which will not be available through the planned programme budget.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
INF129 - INF (17-18) Database Resilience | Planned to start October 2017, Priority 5 |
INF130 - INF (17-18) - Annual DR Review and Tests 17-18 | Planned to start December 2017, Priority 6 |
INF131 - INF (17-18) - Annual Upgrade of Development Tools 17-18 | Planned to start December 2017, Priority 7 |
INF132 - INF (17-18) Application Monitoring Procurement | Discretionary project - funding to be confirmed by sponsor, Priority 9 |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||
Migrate Core Databases to Oracle 12c Category: Compliance
Milestones
RAG Status / RAG change during last month RED |
Report by Chris Konczak for August 2017Achievements this Period
Issues
Next Steps
RAG CommentarySetting project to RED Issue. There are problems found with some application when testing GEN DEV post migration to DEV. These required development input which is resourced to investigate and resolve. Other problems were encountered that required time to diagnose and resolve and document for migration to TEST. Project is RED due to milestones needing revised.
|
||||||||||||||||||||||||||||
INF123 16-17 Provisioning of Python environment Compliance Milestones
RAG Status Green |
Report by Chris Orrell for August 2017Achievements in Last Period
IssuesNext Steps
RAG CommentaryCost is rated amber only to reflect the fact a budget swap is still to be completed, which explains the 26 days unallocated.
|
||||||||||||||||||||||||||||
INF126 Bamboo Recovery Compliance Milestones Milestones will require review based on the outcome / decision made as per proposals submitted to the Project Sponsor / Information Security Team (ISSUE #2), meeting planned 08/09/2017.
RAG Status RED |
Report by Richard Bailey for August 2017
Achievements in Last Period
Issues and RisksNext Steps
RAG Commentary
|
||||||||||||||||||||||||||||
INF127 (AP78-044) Milestones
RAG Status GREEN |
Report by Anne Mathison for August 2017Achievements :
Issues :
Next Steps :
|
||||||||||||||||||||||||||||
INF128 Annual Infrastructure Rationalisation Decommissioning 17/18 Milestones
RAG Status Green |
Report by David Watters for August 2017Achievements
Issues
Next steps
|