May 2016

Report Date
May 2016

IS Applications Infrastructure Programme Report for Programme Owner Stefan Keampf

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: AMBER  

 

 

 

 

 

Section Two: Projects Not Started  

Project InfoProgramme Manager's Commentary

System Monitoring Solution - Pilot

 

The follow on project is now scheduled to start in June.

So less budget this year and potential impact on next year.

AMBER

INF121 Migrate Core Databases to Oracle 12cBrought Forward from 2016/17 - Chris K assigned as PM

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary
INF105 (AP45-053)

Decommission Obsolete Infrastructure

Category: Core Funding

 

Milestones

 

30-Jun-2016Windows decommissioning (15-16) completedDeliver
30-Jun-2016RedHat decommissioning (15-16) completedDeliver
30-Jun-2016Solaris decommissioning (15-16) completedDeliver
14-Jul-2016ClosureClose

 

RAG Status/ RAG change during last month

Project status is GREEN.

Report by David Watters for May 2016

Achievements this Period

  • Further monitoring of CF migrations - most  completed; all now planned or under way
  • Related wiki pages and reports updated

Issues

  • None reported

Next Steps

  • Continue to monitor final round of planned migrations
  • Some applications to be migrated by Technology Management team
 

 

INF110 (AP56-004)

Install Oracle 12c

Category: Compliance

 

Milestones

10-Jun-2016Deployment sign-offDeliver
24-Jun-2016Project closureClose

RAG Status/ RAG change during last month

Project status is GREEN

Report by David Watters for May 2016

Achievements this Period

  • Build of TEST servers completed
  • Build of LIVE servers completed
  • Workshop/handover to Production arranged

Issues

  • Bug detected in DEV backup - patch applied after consultation with Oracle

Next Steps

  • Completion of handover
  • Project closure to be carried out

INF111 (AP56-006)

New SQL Server Database Tier Replacement

Category: Compliance

 

Milestones

10-Jun-2016 (tbc)Consultancy & Design
30-Jun-2016 (tbc)Closure

 

 

 

 

 

RAG Status/ RAG change during last month

Project status is AMBER

Report by Karen Stirling for May 2016

 

Achievements in Last Period

  • Comms Care SQL technician provided SQL Analysis Report received from XMA on 3rd May
  • Review meeting held on 12th May to review report and discuss new solutions and next steps
  • Agreement to opt for dedicated virtual host clustered servers
  • Project Sponsor to complete current cost baseline for management of existing SQL infrastructure this is to be used to compare against other options proposed by XMA
  • Produce draft TAD for host servers
  • Until the new SQL server DB tier is complete, we have built 4 new shared SQL servers using the same format as our existing SQL infrastructure, these are now with Tech Man team to support with assistance to be provided by Dev Tech team

Issues

  • Delay in delivery of host specification and costings from XMA - this is being chased for information as currentlyXMA are unable to receive information from Dell due to mini tender between UoE and Esteem. This has been raised to George Reid at Procurement for assistance. XMA have now provided an alternative solution recommendation and costs these have been forwarded to the project team to discuss next steps.
  • Draft TAD cannot be completed until host specification details regarding licences is provided
  • Review Consultancy and Design together with Closure milestones to ensure project closure remains on target to complete by end of June.

 Next Steps

  • Decision on server purchase to be agreed
  • Present TAD to ITI via framework

 

The project current status is AMBER due to delay in receipt of host server specification to allow purchase decision to be made.

INF113 (AP45-067)

System Monitoring Pilot

Category: Discretionary

 

Milestones

 

27-May-2016Pilot Service 2 - Linux
30-Jun-2016Recommendations
30-Jun-2016Pilot Dashboards
15-Jul-2016Close

 

RAG Status / RAG change during last month

AMBER

Report by Colin Watt for for May 2016

 

Achievements in Last Period

  • The 3rd party tool SquaredUp has been evaluated and confirmed to provide a workaround to the restriction to Internet Explorer previously reported as a showstopper; the tool also provides superior dashboard capability; sample dashboards have been provided for review by project stakeholders - feedback to be incorprated into the recommendations. 

 

Issues

  • No major issues.

 

Next Steps

  • Review budget considering availability of project team and stakeholders.
  • Consolidate feedback on SquaredUp sample dashboards.
  • Write recommendations report.

 

The project current status is AMBER due to delay revisiting and reviewing the Pilot Service 2 milestone.

 

 

INF115 Python Development Platform Implementation

D

Milestones

Target dateTitle
30-Jun-2016Release 1
15-Jul-2016Closure

RAG Status

GREEN

 

Report by Adam Wadee for May 2016

 

Achievements in Last Period

  • At the end of May, Iteration 7 has been completed.
  • In total, 25 user stories have been completed (69 story points).
  • Resourcing with Software Dev is progressing well, no conflicts to report.

Issues

  • The request for additional budget / extended timeline has been approved.

 

Next Steps

  • Continue project into June/July and complete the required stories for Release 1.

 

 

INF116 ASTA Upgrade 15/16

C

Milestones

20-Jun-2016TEST Upgrade Complete
24-Jun-2016Testing Complete
20-Jul-2016LIVE Upgrade Complete (Deployment)
12-Aug-2016Deployment Sign Off
26-Aug-2016Project Closure

RAG Status

RED

Report by Nikki Stuart for May 2016

Achievements:

  • ASTA confirmed that there is no need to move the DB from the current server
  • IS Apps Project Team agreed that the DB will not be moved in this project (supporting PICCL outstanding)
  • Dev Tech resources secured for mid June TEST upgrade and mid July LIVE upgrade
  • Discussion initiated with ASTA to consider remote upgrade by supplier

Issues:

  • Dev Tech resources not available to start TEST upgarde until mid June. This means that the earliest that July could be upgraded by Dev Tech is mid July, which is risky with the Apps end/start of year activities at the end of July. Discussions are underway with ASTA to determine whether they could remotely undertake the upgarde to reduce the risk and the timescales. As it may not be possible to reduce the timelines due to ASTA admins unavailability early July and therefore there is a risk that the upgarde will be delayed to 16/17.(see risk 5)

Next Steps:

  • Confirm upgrade resourcing approach and replan project 
  • Agree TEST and LIVE upgrade dates with ASTA, regardless of approach to upgrading the application they need to undertake a remote upgrade of the DB
  • Update TAD
  • Undertake TEST upgrade

 

Milestones

(are provisional and provided for information only awaiting decision regarding Risk 5 and the upgrade approach)

RAG Status is RED due to delivery date being changed by more than one month.

 

 

INF118 (AP56-005)

JIRA Upgrade 2016

Category: Compliance

 

Milestones

28-Jun-2016Dev config complete
08-Jul-2016Test config complete
15-Jul-2016Integration testing
20-Jul-2016Acceptance sign off
05-Aug-2016LIVE config complete
05-Sep-2016Delivery
20-Sep-2016DSOR / Closure

 

RAG Status / RAG change during last month

AMBER

 

 

Report by Chris Konczak for for May 2016

 

Achievements in Last Period

  • Planning signed off.
  • TAD complete
  • New DEV server build complete, ORACLE 12c and data now in DEV 

 

Issues

  • Project will run into the 16/17 year for deployment resulting in no JIRA upgrade for the 16/17 year.
  • New milestones planed as project sponsor was on sick leave followed by annual leave resulting in the project being AMBER

 

Next Steps

  • Server for TEST and LIVE built and JIRA installed
  • 12c database created in TEST and LIVE
  • DEV JIRA configuration

 

The project current status is AMBER.

INF119 (AP56-047)

Service Resilience Capability

Category: Discretionary

 

Milestones

17-Jun-2016Project Brief
30-Nov-2016Delivery
15-Dec-2016Closure

 

RAG Status / RAG change during last month

GREEN

Report by Karen Stirling for May 2016

 

Achievements in Last Period

  • Planning activities commenced
  • Project brief drafted and reviewed at meeting held 18th May to discuss planning and estimation including resource required to work on project.

Issues

  • From first planning meeting it was clear that we needed key stakeholders to attend a further planning meeting to understand requirements, deliverables etc. from this project. This is to ensure that we have clearly defined and contained scope to take forward.
  • A PICCL has been raised and submitted/approved by WIS to extend the project brief milestone to 17/06/16 this will allow estimation and allocation of resource to project to be confirmed, Project Sponsor and Programme Manager advised of change to project brief submission

Next Steps

  • Estimation agreed and Resource assigned
  • Identify key stakeholders, risks
  • Project brief approval

The project status is GREEN

INF120

Disaster Recovery for Priority Services

Category: Discretionary

 

Milestones

 

15-Jul-2016Initial Priority Services Review
05-Aug-2016DR Document Storage Area ready
21-Oct-2016Priority Services DR Documentation complete
14-Nov-2016Delivery
02-Dec-2016Closure

 

RAG Status / RAG change during last month

GREEN

Report by Karen Stirling for May 2016

 

Achievements in Last Period

  • Planning activities completed following review of project brief, plan and estimates
  • Stakeholder and Risk Logs created
  • High level review of disaster recovery plans available for Top and Medium priority services to assist completion of project brief
  • Project brief signed off by project team and approved at WIS on 03/06/16
  • Resource allocated from Dev Tech and Tech Man
  • Project team meetings set up for every 2 weeks

Issues

  • N/A

Next Steps

  • Commence Analysis activity to review all applications & components which make up the Top and Medium priority services (27 in total)
  • Review storage options for a master DR document which can be stored off site

 

The project status is GREEN

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

INF108 (AP45-034)

Automated Server Builds

Closure approved 11 September 2015.

INF112 (AP56-007)

Build and Configure new ColdFusion Version [15/16]

Closure approved December 2015

INF114: Implementation of EASE Second Challenge

Closure approved December 2015
INF117 (AP56-005) Bamboo UpgradeClosure approved June 2016