April 2016

Report Date
April 2016

IS Applications Infrastructure Programme Report for Programme Owner Stefan Keampf

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: AMBER  

As we move to the last quarter, most projects now have a project manager but many of them are starting late or being picked up by the new project managers later than planned.

Many requests for Dev Tech resource  in particular - are either still to be made by the project managers or still waiting to be assigned by the resource manager.

Also, we have a request for a new in-year project to upgrade PHP for EdWeb.  The days are available due to descoping of INF113 and subsequent project, but the commitment from Dev Tech is not clear.

Accordingly, sufficient risk to set programme as Amber.

 

 

 

 

 

Section Two: Projects Not Started  

Project InfoProgramme Manager's Commentary

System Monitoring Solution - Pilot

 

The follow on project is now scheduled to start in June.

So less budget this year and potential impact on next year.

AMBER

INF121 Migration to Oracle 12cBrought Forward from 2016/17 - waiting for a PM

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary
INF105 (AP45-053)

Decommission Obsolete Infrastructure

Category: Core Funding

 

Milestones

 

30-Jun-2016Windows decommissioning (15-16) completedDeliver
30-Jun-2016RedHat decommissioning (15-16) completedDeliver
30-Jun-2016Solaris decommissioning (15-16) completedDeliver
14-Jul-2016ClosureClose

 

RAG Status/ RAG change during last month

Project status is GREEN.

Report by David Watters for April 2016

Achievements this Period

  • Further monitoring of CF migrations - some completed; all now planned or under way
  • Related wiki pages and reports updated

Issues

  • None reported

Next Steps

  • Continue to monitor planned migrations
  • DRPS migration to be completed
  • Some Windows servers to be migrated by Technology Management team
 

 

INF110 (AP56-004)

Install Oracle 12c

Category: Compliance

 

Milestones

20-May-2016TEST environment completeAccept
03-Jun-2016LIVE environment completeDeliver
10-Jun-2016Deployment sign-offDeliver
24-Jun-2016Project closureClose

RAG Status/ RAG change during last month

Project status is RED because the remaining milestones have been revised

Report by David Watters for April 2016

 

Achievements this Period

  • Migration of Wiki database carried out for COM026
  • Build of TEST servers continued
  • Initial build of LIVE servers started by ITI

Issues

  • Problems with AT TEST server - build of TEST delayed
  • Milestones replanned

Next Steps

  • Completion of build of TEST servers
  • Build of LIVE servers 
  • Testing of procedures and handover to Production staff

INF111 (AP56-006)

New SQL Server Database Tier Replacement

Category: Compliance

 

Milestones

29-Apr-2016Analysis
31-May-2016Consultancy & Design
10-Jun-2016Closure

 

 

 

 

 

RAG Status/ RAG change during last month

Project status is GREEN

Report by Karen Stirling for April 2016

 

Achievements in Last Period

  • Statement of works approved by Project Sponsor for SQL Audit - 5 days effort (3 onsite / 2 complete SQL report.
  • Database analysis [76 servers and 850 databases] identified for SQL audit
  • Comms Care SQL technician onsite activity completed between 20-22 April, audit report expected 29th April
  • Project Sponsor to complete current cost baseline for management of existing SQL infrastructure this is to be used to compare against other options proposed by XMA
  • Remaining milestones dates agreed for project

 

Issues

N/A

 

Next Steps

  • Report on findings / recommendations to be provided by xma Consultant
  • Decision on server purchase to be agreed by end of May

 

The project current status is GREEN

INF113 (AP45-067)

System Monitoring Pilot

Category: Discretionary

 

Milestones

 

27-May-2016Pilot Service 2 - Linux
withdrawnPilot Service 3 - Corporate
30-Jun-2016Recommendations
30-Jun-2016Pilot Dashboards
15-Jul-2016Close

 

RAG Status / RAG change during last month

AMBER

Report by Colin Watt for for April 2016

 

Achievements in Last Period

  • Basic dashboards for Learn built against Test (milestone not complete).
  • Face to face meeting with all key stakeholders to cover the technical and policy issues and agree whether to continue with SCOM / the project (agreement was to continue but to redefine milestones).

 

Issues

  • No major issues - the team agreed a plan to seek workarounds for the technical challenges on the project.

 

Next Steps

  • Reduce budget by 50d to 70d.
  • Focus on workarounds and more detailed responses to technical challenges, including dashboards, in May.
  • Delay writing recommendations report unil June based on getting better answers to the technical questions in May.

 

The project current status is AMBER due to the agreed changes to milestones including delivery.

INF115 Python Development Platform Implementation

D

Milestones

Target dateTitle
30-Jun-2016Release 1
15-Jul-2016Closure

RAG Status

AMBER

 

Report by Adam Wadee for April 2016

 

Achievements in Last Period

  • At the end of April, Iteration 5 has been completed, achieving the first milestone: Pre-Requisites.
  • In total, 17 user stories have been completed (45 story points).
  • Resourcing issues in Software Dev have eased, with approx 3 days per week assigned to the project.

Issues

  • A request for additional budget has been submitted to Programme Manager.  This will be needed to continue developments into June, and to complete Release 1.
  • The main resource from Dev Tech is on leave most of May, so obtaining cover at required level is a risk.

 

Next Steps

  • Start the next phase of the project: Release 1 and complete Iterations 6 and 7 during May.
  • Obtain additional effort which will allow the project to continue into June and complete the required stories for Release 1.

 

The RAG status is AMBER as we require additional budget to continue the project into June and complete Release 1.

 

INF116 ASTA Upgrade 15/16

C

Milestones

04-May-2016Infrastructure Decision
27-May-2016TEST Upgrade Complete
13-Jun-2016Testing Complete
17-Jun-2016LIVE Upgrade Complete (Deployment)
19-Jul-2016Deployment Sign Off
22-Jul-2016Project Closure

RAG Status

GREEN

Report by Susan Duff for April 2016

Achievements:

  • New PM assigned
  • Project Brief signed off
  • End of Planning milestone achieved
  • Discussion held on infrastructure options
  • Contact made with ASTA suppliers re their tasks

Issues:

  • None

Next Steps:

  • Agree database server recommendation
  • Agree TEST and LIVE upgrade dates with ASTA
  • Plan window for LIVE upgrade between MI reporting and other key business activities
  • Secure resources in ASTA

 

 

 

INF117 (AP56-005) Bamboo Upgrade

C

 

Milestones

12-May-2016CITESTER (dev,beta, test and live) Upgraded
19-May-2016Closure

 

RAG Status / RAG change during last month RED

Report by Gillian Henderson for for April 2016

Achievements in Last Period

  • Environment setup for dev,beta, test and live CITESTER migrations
  • Started upgrade of CITESTER dev environment to CF11.

Issues

  •  Issue getting Dev Team and Dev Tech resources to complete the CITESTER migrations. See PICCL 2 (https://www.projects.ed.ac.uk/project/inf117/issues/2)
  • CITESTER and Closure Milestones moved as a consequence (however the main project objectives achived as Bamboo upgrade complete)

Next Steps

  • Complete upgrade of CITESTER dev environment.
  • Upgrade beta, test and live CITESTER to CF11
  • Closure  

Status RED as milestone moved back a month.  

INF118 (AP56-005)

JIRA Upgrade 2016

Category: Compliance

 

Milestones

22-Apr-2016End of Planning
30-Jun-2016Delivery
14-Jul-2016Closure

 

RAG Status / RAG change during last month

AMBER

 

 

Report by Chris Konczak for for April 2016

 

Achievements in Last Period

  • Agree resourcing.
  • Review milestones and estimates.
  • Handover to new project manager

 

Issues

  • Issues with the upgrade to DEV JIRA on old infrastructure
  • Delay in getting planning signed off due to new PM picking this up past the original planning sign off milestone

 

Next Steps

  • New milestone and sign off in May for Planning
  • Decision on continuing with DEV old infrastructure or new infrastructure

 

The project current status is AMBER.

INF119 (AP56-047)

Service Resilience Capability

Category: Discretionary

 

Milestones

31-May-2016Project Brief
30-Nov-2016Delivery
15-Dec-2016Closure

 

RAG Status / RAG change during last month

GREEN

Report by Karen Stirling for April 2016

 

Achievements in Last Period

  • Project Manager assigned
  • Project website set up
  • Initial meeting with Project Sponsor and key stakeholder

Issues

  • N/A

Next Steps

  • Start planning activities
  • Complete project brief

The project is GREEN

INF120

Disaster Recovery for Priority Services

Category: Discretionary

 

Milestones

31-May-2016Project Brief
30-Nov-2016Delivery
15-Dec-2016Closure

 

RAG Status / RAG change during last month

GREEN

Report by Karen Stirling for April 2016

 

Achievements in Last Period

  • Project Manager assigned
  • Project website set up
  • Initial meeting with Project Sponsor and key stakeholder

Issues

  • N/A

Next Steps

  • Start planning activities
  • Complete project brief

The project is GREEN

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

INF108 (AP45-034)

Automated Server Builds

Closure approved 11 September 2015.

INF112 (AP56-007)

Build and Configure new ColdFusion Version [15/16]

Closure approved December 2015

INF114: Implementation of EASE Second Challenge

Closure approved December 2015