April 2016
- Report Date
- April 2016
IS Applications Infrastructure Programme Report for Programme Owner Stefan Keampf
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: AMBER
As we move to the last quarter, most projects now have a project manager but many of them are starting late or being picked up by the new project managers later than planned.
Many requests for Dev Tech resource in particular - are either still to be made by the project managers or still waiting to be assigned by the resource manager.
Also, we have a request for a new in-year project to upgrade PHP for EdWeb. The days are available due to descoping of INF113 and subsequent project, but the commitment from Dev Tech is not clear.
Accordingly, sufficient risk to set programme as Amber.


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
System Monitoring Solution - Pilot
| The follow on project is now scheduled to start in June. So less budget this year and potential impact on next year. AMBER |
| INF121 Migration to Oracle 12c | Brought Forward from 2016/17 - waiting for a PM |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||
| INF105 (AP45-053) Decommission Obsolete Infrastructure Category: Core Funding
Milestones
RAG Status/ RAG change during last month Project status is GREEN. | Report by David Watters for April 2016Achievements this Period
Issues
Next Steps
| ||||||||||||
Install Oracle 12c Category: Compliance
Milestones
RAG Status/ RAG change during last month Project status is RED because the remaining milestones have been revised | Report by David Watters for April 2016
Achievements this Period
Issues
Next Steps
| ||||||||||||
New SQL Server Database Tier Replacement Category: Compliance
Milestones
RAG Status/ RAG change during last month Project status is GREEN | Report by Karen Stirling for April 2016
Achievements in Last Period
Issues N/A
Next Steps
The project current status is GREEN | ||||||||||||
System Monitoring Pilot Category: Discretionary
Milestones
RAG Status / RAG change during last month AMBER | Report by Colin Watt for for April 2016
Achievements in Last Period
Issues
Next Steps
The project current status is AMBER due to the agreed changes to milestones including delivery. | ||||||||||||
INF115 Python Development Platform Implementation D Milestones
RAG Status AMBER
| Report by Adam Wadee for April 2016
Achievements in Last Period
Issues
Next Steps
The RAG status is AMBER as we require additional budget to continue the project into June and complete Release 1.
| ||||||||||||
INF116 ASTA Upgrade 15/16 C Milestones
RAG Status GREEN | Report by Susan Duff for April 2016Achievements:
Issues:
Next Steps:
| ||||||||||||
INF117 (AP56-005) Bamboo Upgrade C
Milestones
RAG Status / RAG change during last month RED | Report by Gillian Henderson for for April 2016Achievements in Last Period
Issues
Next Steps
Status RED as milestone moved back a month. | ||||||||||||
JIRA Upgrade 2016 Category: Compliance
Milestones
RAG Status / RAG change during last month AMBER
| Report by Chris Konczak for for April 2016
Achievements in Last Period
Issues
Next Steps
The project current status is AMBER. | ||||||||||||
Service Resilience Capability Category: Discretionary
Milestones
RAG Status / RAG change during last month GREEN | Report by Karen Stirling for April 2016
Achievements in Last Period
Issues
Next Steps
The project is GREEN | ||||||||||||
Disaster Recovery for Priority Services Category: Discretionary
Milestones
RAG Status / RAG change during last month GREEN | Report by Karen Stirling for April 2016
Achievements in Last Period
Issues
Next Steps
The project is GREEN |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Automated Server Builds | Closure approved 11 September 2015. |
Build and Configure new ColdFusion Version [15/16] | Closure approved December 2015 |
| Closure approved December 2015 |
