| Project Info | Project Manager's Commentary |
| INF105 (AP45-053) Decommission Obsolete Infrastructure Category: Core Funding Milestones RAG Status/ RAG change during last month Project status is GREEN. | Report by David Watters for March 2016Achievements this Period- Further monitoring of CF migrations - all now planned or under way
- Related wiki pages and reports updated
- Agreement on short-term move for PURE
IssuesNext Steps- Continue to monitor planned migrations
- DRPS migration to be completed
|
INF110 (AP56-004) Install Oracle 12c Category: Compliance Milestones RAG Status/ RAG change during last month Project status is RED because the milestones have to be revised and extra effort will be required. These are due to the development work requiring more effort than was originally estimated. | Report by David Watters for March 2016 Achievements this Period- Analysis & Build work signed off - DEV environment now ready
- Migration process documented and tested
- Documentation updated and reviewed
- Build of TEST servers started
- Acquisition of LIVE servers agreed with ITI
Issues- Additional effort required - budget to be revised
- Outstanding milestones pushed back
- Problems with AT TEST server - handover delayed
Next Steps- Completion of build of TEST servers
- Ordering of LIVE servers
- Testing of procedures and handover to Production staff
|
INF111 (AP56-006) New SQL Server Database Tier Replacement Category: Compliance Milestones (to be confirmed) RAG Status/ RAG change during last month Project status is AMBER | Report by Karen Stirling for for March 2016 Achievements in Last Period - Project Sponsor has advised his top 5 outcomes, these have to be reviewed with project stakeholders for consistancy in approach
- Database analysis completed to identify current list of databases, details contained in spreadsheet initial numbers noted as 651 databases to allow Statement of Works to be provided by Comms Care / XMA
- Statement of works received for SQL Audit - this has been reviewed by Project Sponsor / Programme Manager and some further clarity required with XMA, this is being feed back to Account Manager
- Initial dates for audit to complete proposed as 4th / 11th April however there are a number of ITI and Network essential maintenance being undertaken over that period so it has been suggested to SQLTechnician week commencing 18th April for onsite activity.
- Project Sponsor tasked to complete current cost baseline for management of existing SQL infrastructure this is to be used to compare against other options proposed by XMA
Issues - Further PICCL to be submitted to revise Analysis now expected to complete 22/4/16 and Design milestones to be confirmed on completion of Audit and Recommendation report from XMA
- Due to delays in reaching a decision on infrastructure Project Sponsor / Technology Management has agreed for 4 VM servers (2x live, 2x test) to host SQL Server dbs until INF111 project completes. Some days to be charged to project for build activity Dev Tech to provide estimates to record change in project.
Next Steps - Complete SQL Audit
- Report on findings/ recommendations
The project current status is AMBER as milestones to be confirmed for completion of Findings/ Recommendations to be reported |
INF113 (AP45-067) System Monitoring Pilot Category: Discretionary Milestones (to be revised pending project status review early April) RAG Status / RAG change during last month RED | Report by Colin Watt for for March 2016 Achievements in Last Period - Basic dashboards for Learn built against Test (milestone not complete).
- Microsoft "Chalk & Talk" sessions completed with ITI w/c 14/03/16.
Issues - MS System Center UI only compatible with Internet Explorer; an inconvenience but outweighed by benefits; however this could be an issue for some IS stakeholders; likewise presentation on non-Windows PCs; there do appear to be Third Party solutions which avoid the need for IE (and would assist with developing more sophisticated dashboard capability than is available out of the box), with associated licensing costs.
- PM has agreed with Project Sponsor that a face to face meeting with all key stakeholders is necessary to cover the above and agree whether to continue with SCOM / the project.
- PM has agreed with Project Sponsor to liaise with ITI to arrange a conference call with Microsoft to explore options for the above, ahead of the face to face meeting.
Next Steps - Project team and key stakeholders to meet and cover above issues; decide whether to continue or halt project.
- (If agreement is to continue) review budget, estimates, and replan milestones.
The project current status is RED due to uncertainty on SCOM integration. |
INF115
Python Development Platform Implementation D Milestones RAG Status AMBER | Report by Adam Wadee for March 2016 Achievements in Last Period - At the end of March, Iteration 3 has been completed.
- In total, 11 user stories have been completed (34 story points).
Issues - Two resource conflicts have been recorded due to work being needed on TTU011 and COM022.
- Project milestones have been revised, meaning the RAG status is Amber.
Next Steps - Start Iteration 4 which will see the completion of the Pre-requisites phase.
- Start Iteration 5 (Initial Consultation) phase.
RAG status AMBER as milestones have changed. |
INF116
ASTA Upgrade 15/16 C Milestones RAG Status AMBER | Report by Nikki Stuart for March 2016Achievements:- Draft brief circulated to project stakeholders for review and sign off
- Initial ASTA plan created and development technology tasks requested.
Issues:- Delay to completing planning due to conflicts within Project Services. The new PM will start on 11th April and the project is now expected to progress as planned. (RESOLVED)
Next Steps:- Sign off project brief
- secure resources in ASTA
- agree database server recommendation
- plan window for LIVE upgrade between MI reporting and other key business activities
- agree TEST and LIVE upgrade dates with ASTA
Project Status - AMBER due to slippage of planning milestone, now resolved. |
INF117
Bamboo Upgrade C Milestones RAG Status GREEN |
| Report by Gillian Henderson for for March 2016Achievements in Last Period Issues - Utililty belt plugin not supported in new version on Bamboo. Timetabling was the only application making use of this functaionality.
Jonny has updated Timetabling SATSTAGE and Bookable Rooms Feed plans and they no longer use the third party plugin (See Issue https://www.projects.ed.ac.uk/project/inf117/issues/1
Next Steps |
INF118 (AP56-005) JIRA Upgrade 2016 Category: Compliance Milestones (to be agreed) RAG Status / RAG change during last month GREEN | Report by Colin Watt for for March 2016 Achievements in Last Period - Project Website set up.
- Initial discussion (PM and Service Owner).
- Familiarisation with previous upgrade project.
Issues Next Steps - Kickoff with key stakeholders.
- Agree resourcing.
- Complete Planning.
- Review milestones and estimates.
The project current status is GREEN. |