IS Applications Infrastructure Programme Report for Programme Owner Stefan Keampf

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: GREEN  

Several projects arer Red/Amber but most of them expected to move back to Green.

The final project INF119 for 15/16 wil start in May.

Two 16/17 projects INF120 and INF121 brought forward as planned and project managers planned in for these.

INF113 has significant issues - not clear how this project will move forward just now.

No budget issues other than the proejct folowing on from INF113 is at risk.

 

 

 

 

 

 

Section Two: Projects Not Started  

Project InfoProgramme Manager's Commentary

System Monitoring Solution - Pilot

 

The follow on project is now scheduled to start in June.

So less budget this year and potential impact on next year.

AMBER

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary
INF105 (AP45-053)

Decommission Obsolete Infrastructure

Category: Core Funding

 

Milestones

 

30-Jun-2016Windows decommissioning (15-16) completedDeliver
30-Jun-2016RedHat decommissioning (15-16) completedDeliver
30-Jun-2016Solaris decommissioning (15-16) completedDeliver
14-Jul-2016ClosureClose

 

RAG Status/ RAG change during last month

Project status is GREEN.

Report by David Watters for March 2016

Achievements this Period

  • Further monitoring of CF migrations - all now planned or under way
  • Related wiki pages and reports updated
  • Agreement on short-term move for PURE

Issues

  • None reported

Next Steps

  • Continue to monitor planned migrations
  • DRPS migration to be completed
 

 

INF110 (AP56-004)

Install Oracle 12c

Category: Compliance

 

Milestones

22-Apr-2016Testing sign-offAccept
28-Apr-2016Deployment to TESTDeliver
05-May-2016Deployment sign-offDeliver
19-May-2016Project closureClose

 

RAG Status/ RAG change during last month

Project status is RED because the milestones have to be revised and extra effort will be required. These are due to the development work requiring more effort than was originally estimated.

Report by David Watters for March 2016

 

Achievements this Period

  • Analysis & Build work signed off - DEV environment now ready
  • Migration process documented and tested
  • Documentation updated and reviewed
  • Build of TEST servers started
  • Acquisition of LIVE servers agreed with ITI

Issues

  • Additional effort required - budget to be revised
  • Outstanding milestones pushed back
  • Problems with AT TEST server - handover delayed

Next Steps

  • Completion of build of TEST servers
  • Ordering of LIVE servers 
  • Testing of procedures and handover to Production staff

INF111 (AP56-006)

New SQL Server Database Tier Replacement

Category: Compliance

 

Milestones (to be confirmed)

22-Apr-2016Analysis 
TBCConsultancy & Design 

 

 

 

 

 

 

RAG Status/ RAG change during last month

Project status is AMBER

Report by Karen Stirling for for March 2016

 

Achievements in Last Period

  • Project Sponsor has advised his top 5 outcomes, these have to be reviewed with project stakeholders for consistancy in approach
  • Database analysis completed to identify current list of databases, details contained in spreadsheet initial numbers noted as 651 databases to allow Statement of Works to be provided by Comms Care / XMA
  • Statement of works received for SQL Audit - this has been reviewed by Project Sponsor / Programme Manager and some further clarity required with XMA, this is being feed back to Account Manager
  • Initial dates for audit to complete proposed as 4th / 11th April however there are a number of ITI and Network essential maintenance being undertaken over that period so it has been suggested to SQLTechnician week commencing 18th April for onsite activity.
  • Project Sponsor tasked to complete current cost baseline for management of existing SQL infrastructure this is to be used to compare against other options proposed by XMA

 

Issues

  • Further PICCL to be submitted to revise Analysis now expected to complete 22/4/16 and Design milestones to be confirmed on completion of Audit and Recommendation report from XMA
  • Due to delays in reaching a decision on infrastructure Project Sponsor / Technology Management has agreed for 4 VM servers (2x live, 2x test) to host SQL Server dbs until INF111 project completes. Some days to be charged to project for build activity Dev Tech to provide estimates to record change in project.

 

Next Steps

  • Complete SQL Audit
  • Report on findings/ recommendations

 

The project current status is AMBER as milestones to be confirmed for completion of Findings/ Recommendations to be reported

INF113 (AP45-067)

System Monitoring Pilot

Category: Discretionary

 

Milestones

(to be revised pending project status review early April)

03-Mar-2016Pilot Service 2 - Linux
07-Apr-2016Pilot Service 3 - Corporate
05-May-2016Recommendations
05-May-2016Delivery
19-May-2016Close

 

RAG Status / RAG change during last month

RED

Report by Colin Watt for for March 2016

 

Achievements in Last Period

  • Basic dashboards for Learn built against Test (milestone not complete).
  • Microsoft "Chalk & Talk" sessions completed with ITI w/c 14/03/16.

 

Issues

  • MS System Center UI only compatible with Internet Explorer; an inconvenience but outweighed by benefits; however this could be an issue for some IS stakeholders; likewise presentation on non-Windows PCs; there do appear to be Third Party solutions which avoid the need for IE (and would assist with developing more sophisticated dashboard capability than is available out of the box), with associated licensing costs.
  • PM has agreed with Project Sponsor that a face to face meeting with all key stakeholders is necessary to cover the above and agree whether to continue with SCOM / the project.
  • PM has agreed with Project Sponsor to liaise with ITI to arrange a conference call with Microsoft to explore options for the above, ahead of the face to face meeting.

 

Next Steps

  • Project team and key stakeholders to meet and cover above issues; decide whether to continue or halt project.
  • (If agreement is to continue) review budget, estimates, and replan milestones. 

 

The project current status is RED due to uncertainty on SCOM integration.

INF115 Python Development Platform Implementation

D

Milestones

Target dateTitle
15-Apr-2016Pre-requisites
13-May-2016Initial Consultation
17-Jun-2016Release 1
30-Jun-2016Closure

RAG Status

AMBER

 

Report by Adam Wadee for March 2016

 

Achievements in Last Period

  • At the end of March, Iteration 3 has been completed.
  • In total, 11 user stories have been completed (34 story points).

Issues

  • Two resource conflicts have been recorded due to work being needed on TTU011 and COM022.
  • Project milestones have been revised, meaning the RAG status is Amber.

 

Next Steps

  • Start Iteration 4 which will see the completion of the Pre-requisites phase.
  • Start Iteration 5 (Initial Consultation) phase.

 

RAG status AMBER as milestones have changed.

INF116 ASTA Upgrade 15/16

C

Milestones

11-Apr-2016End of Planning
15-Apr-2016Infrastructure Decision
13-May-2016Testing Complete
27-May-2016TEST Upgrade Complete
17-Jun-2016LIVE Upgrade Complete (Deployment)
19-Jul-2016Deployment Sign Off
22-Jul-2016Project Closure

RAG Status

AMBER

Report by Nikki Stuart for March 2016

Achievements:

  • Draft brief circulated to project stakeholders for review and sign off
  • Initial ASTA plan created and development technology tasks requested. 

Issues:

  • Delay to completing planning due to conflicts within Project Services. The new PM will start on 11th April and the project is now expected to progress as planned.  (RESOLVED)

Next Steps:

  • Sign off project brief
  • secure resources in ASTA
  • agree database server recommendation
  • plan window for LIVE upgrade between MI reporting and other key business activities
  • agree TEST and LIVE upgrade dates with ASTA

 

Project Status - AMBER due to slippage of planning milestone, now resolved. 

 

 

 

INF117 Bamboo Upgrade

C

Milestones

Target dateTitle
03-Mar-2016End of Planning
11-Mar-2016Build and Acceptance
21-Mar-2016Delivery
24-Mar-2016Deployment Sign Off
31-Mar-2016CITESTER (dev,beta, test and live) Upgraded
14-Apr-2016Closure

RAG Status

GREEN

 

 

Report by Gillian Henderson for for March 2016

Achievements in Last Period

 

Issues

  •  Utililty belt plugin not supported in new version on Bamboo.  Timetabling was the only application making use of this functaionality. Jonny has updated Timetabling SATSTAGE and Bookable Rooms Feed plans and they no longer use the third party plugin (See Issue https://www.projects.ed.ac.uk/project/inf117/issues/1

 

Next Steps

INF118 (AP56-005)

JIRA Upgrade 2016

Category: Compliance

 

Milestones

(to be agreed)

 

RAG Status / RAG change during last month

GREEN

 

 

Report by Colin Watt for for March 2016

 

Achievements in Last Period

  • Project Website set up.
  • Initial discussion (PM and Service Owner).
  • Familiarisation with previous upgrade project.

 

Issues

  • No major issues.

 

Next Steps

  • Kickoff with key stakeholders.
  • Agree resourcing.
  • Complete Planning.
  • Review milestones and estimates.

 

The project current status is GREEN.

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

INF108 (AP45-034)

Automated Server Builds

Closure approved 11 September 2015.

INF112 (AP56-007)

Build and Configure new ColdFusion Version [15/16]

Closure approved December 2015

INF114: Implementation of EASE Second Challenge

Closure approved December 2015