January 2016
- Report Date
- January 2016
IS Applications Infrastructure Programme Report for Programme Owner Stefan Keampf
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
Several projects pushing back milestones at present, but overall prgoramme on course to complete work within year and within budget, with no impact or risks to services.

Resource Sumary

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
System Monitoring Solution - Pilot
| INF107 having completed, the next project will split into a Pilot phase to validate the technical solution and the process changes recommended, before procurement/implementation. We had hoped to start this in 2014/15 but due to other priorities and resource constraints, will start in Q4 2015 once we have discussed with colleagues in ITI.
|
| Service Resilience Capability | Staff and students have been operating more and more on a 24x7x365 basis. Service availability is key to ensure this. While our infrastructure is robust, issues to arise and as we do not have personnel on hand to the same timeframe, an automated facility is required. To start Q1 2016 |
| Annual upgrades of development tools (JIRA, Bamboo, etc) (15-16) | We have taken on the above products as part of our core workflow for project (and support) delivery in recent times. As such they are essential to our ability to successfully deliver change within the University. Failure to keep the products up to date and in a supportable position exposes us to the risk of serious issues with the software that may affect their ability to run and operate in our environment. To start Q1 2016 |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | |||||||||||||||
| INF105 (AP45-053) Decommission Obsolete Infrastructure Category: Core Funding
Milestones
RAG Status/ RAG change during last month Project status is GREEN. | Report by David Watters for January 2016Achievements this Period
Issues
Next Steps
| |||||||||||||||
Install Oracle 12c Category: Compliance
Milestones
RAG Status/ RAG change during last month Project status is RED because of the changes to the outstanding milestones in the reporting month | Report by David Watters for January 2016
Achievements this Period
Issues
Next Steps
| |||||||||||||||
New SQL Server Database Tier Replacement Category: Compliance
Milestones (to be confirmed)
RAG Status/ RAG change during last month Project status is RED as milestones to be confirmed and change to scope | Report by Karen Stirling for for January 2016
Achievements in Last Period
Issues
Next Steps
The project current status is RED | |||||||||||||||
System Monitoring Pilot Category: Discretionary
Milestones
RAG Status / RAG change during last month GREEN | Report by Colin Watt for for January 2016
Achievements in Last Period
Issues
Next Steps
The project current status is GREEN | |||||||||||||||
INF115 Python Development Platform Implementation D Milestones
RAG Status GREEN
| Report by Adam Wadee for January 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Automated Server Builds | Closure approved 11 September 2015. |
Build and Configure new ColdFusion Version [15/16] | Closure approved Decemebr 2015 |
| Closure approved Decemebr 2015 |