Report for July 2017

Report Date
July 2017

Morna Findlay (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)

 

 Section One: Programme Commentary, RAG and Resources Update 

 

Commentary

 

The programme manager considers that overall the programme is GREEN, as all projects which were not withdrawn were delivered this year and within the programme budget.

As the remaining project in the programme  (HRS092) was already fully resourced, the HR Balance row has been reduced  from 9 days to 0 days: 9 days were transferred to the USG portfolio budget.

This has resulted in a reduction to the programme budget from 230 days to 221 days.

 

Risk - Erecruitment Licencing - NCA required

The e-recruitment   contract  needs to be updated by October 2017. The original 5 year contract concludes in October and any extension for a further year  must be arranged by October.  An extension would be done as a Non-Competitive Action (NCA)  and this is essential to be licensed to continue using eRecruitment.  

 

Projects in Progress: summary

 

HRS091 - Closed this month.

HRS092 - GREEN

 

Forward Look for August   2017

 

 

 

 

Resources to 31/07/2017

 

 

HRS092 is the only remaining project this year. It is planned to close in  17/18.

 

 

 Section Two: Projects Not Started

 

There are no approved projects planned  to this month.  The following projects will start later in the year.

AP17-18:    APEX Tomcat 7 End of Life
AP17-18:    HESA Staff Return 17/18

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

 

HRS091 (AP56-049)

Working Time Capture and Reporting ( was Enhancing Employment Technical Implementation)

Category: Core Funded

Compliance

Milestones 

None

            

RAG Status

BLUE

Report by Susan Duff for July 2017

Achievements in Last Period

  • Closure approved

Issues

  • No issues

Next Period

  • None

HRS092 (AP67-034) HESA Staff Return 16/17

Category : Core-funded

Compliance

Milestones

29-Sep-2017 Submit HESA Return
13-Oct-2017 Commit
10-Nov-2017 Final Submission
04-Dec-2017 Closure

 RAG Status

GREEN

Report by Anne Mathison for July 2017

Achievements

DEV and TEST have been refreshed during JULY in preparation for HESA LIVE Testing and checking out any issues that arise in  August.

RESAST has had the 31st July file provided loaded on 1-Aug in preparation for HESA Live Testing

Issues

  • None

Next Steps

  • Support HESA testing

Project has a RAG status of GREEN

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

AP67-035 Upgrade eRecruitment Database to Oracle 12c

CategoryL Compliance

This project has been withdrawn from the  current year as the end. of life for Oracle 11g has been extended till 2020 . There may be no requirement for the upgrade if erecruitment is replaced. This project will  therefore be planned for  18/19-19/20.

HRS090 (AP56-025)

HESA Staff Return 15/16

Category:Compliance

Report by Anne Mathison

Project Closure Milestone achieved on 25-Nov-16, Project Completion Report available on the website

HRS086 eRecruitment Proof of Concept

Category: Discretionary, Funded

Report by Susan McKeown

Project Closure Milestone achieved on 25-Aug-15 Project's Completion Report is available on the website.

HRS085 HESA Staff Return 14/15

Category: Compliance

Report by Anne Mathison

Project Closure Milestone achieved on 20-Nov-15 Project's Completion Report is available on the website.

HRS087 HR Reward Calculator

Category: Funded

Report by Susan McKeown

Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website.

HRS088 HR Transformation: Governance and Planning

Category: Compliance

Report by Susan McKeown

Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website

HRS084 Enhancing Employment Analysis

Category: Discretionary

Report by Franck Bergeret

Project Closure Milestone achieved on 18-Feb-16 Project's Completion Report is available on the website

HRS090 HESA Staff Return 15/16

Category : Compliance

Report  by Anne Mathison

Project Closure Milestone achieved on 24-Nov-16 Project's Completion Report  is available on the website

HRS091 Erecruitment Upgrade 

Report by Muriel Mewisson

Project Closure Milestone achieved on 2-Jun-2017 Project's Completion Report  is available on the website

HRS091 (AP56-049)

Working Time Capture and Reporting

Report by Susan Duff

Project Closure Milestone achieved on 13-Jul-2017. Project's Completion Report is available on the website.

AttachmentSize
Image icon hrs-res-july.jpg134.52 KB
Image icon hrs-flook-july.jpg238.21 KB