Report for April 2017

Report Date
April 2017

Morna Findlay (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

 

Commentary

HRS089 - AMBER  as closure milestone delayed.

HRS091 - RED  as new budget and milestones approved and final report not signed off in LIVE

HRS092 - GREEN

 

Forward Look for April 2017

 

 

 

Resources to 30/04/2017

 

With the postponement  until future years of the upgrade of  Erecruitment  to Oracle 12c, there are  a significant number of days

remaining in the balance row which are currently unallocated.  New in-year projects should fall under the compliance category and the

programme manager is exploring with the business whether the delivery of three reports dropped from HRS077 can be delivered in a new in-year project this year.

 

 

 

 

 

 Section Two: Projects Not Started

 

There are no approved projects waiting to start. 

 

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HRS089 (AP56-907)

eRecruitment Upgrade

 

Category: Funded

Milestones

5-May-2017 Closure

 

RAG Status

GREEN

 

Report by Muriel Mewissen for April 2017

Achievements in the last period

Issues

  • None

Next Steps

  • Project report and closure

 

HRS091 (AP56-049)

Working Time Capture and Reporting ( was Enhancing Employment Technical Implementation)

Category: Core Funded

Compliance

Milestones are draft and still to be agreed with the Project Sponsor

12/5/17                Fix for data issues complete

15/5/17                eTime Report re-tested

18/5/17                eTime Report Deployment complete

24/5/17                eTime Report Deployment Sign Off

31/5/17                Closure

RAG Status

RED

Report by Susan Duff for April 2017

Achievements in Last Period

  • Re-deployed eTime report to LIVE after job-segment 2 issue resolved
  • Issue raised re data returned when running report against live data using date filter
  • Resources booked to investigate and resolve issue
  • Additional tasks planned and revised milestones drafted
  • Estimate for additional days made
  • Revised milestones and additional days required flagged to Project Sponsor for discussion and approval

Issues

  • The report is returning data from outwith the selected month. A fix had been made. Being checked again. JIRA HRS091-11 open

  • When investigating the issue with the report data, the following were also identified and require to be fixed JIRA HRS091-12 open

             - date search filter returning incorrect data over year end. Should be a month plus year start and end, ie. 4-2016 and 3-2017. Not high priority - report will run monthly.

            - job segment2 and org hierarchy queries will always return the value as at run date rather than date filter date.

Next Period

  • Resolve issues raised with report filter and values for job segment 2 and org hierarchy
  • Re-test eTime report
  • Deploy eTime Report to LIVE
  • Arrange Deployment Sign Off
  • Project closure

Project has a RAG status of Red (cost) as additional days needed to resolve issue identified when report run on live data

 

HRS092 (AP67-034) HESA Staff Return 16/17

Category : Core-funded

Compliance

Milestones

28-Jul-2017 First Deployment
29-Sep-2017 Submit HESA Return
13-Oct-2017 Commit
10-Nov-2017 Final Submission
04-Dec-2017 Closure

 RAG Status

AMBER

Report by Anne Mathison for April 2017

Achievements:

  • Completed Initial Acceptance Testing
  • First deployment to LIVE has taken place
  • Completed requested change to RESAST - to return correct values, in DEV (HRS092-8)
  • Implemented requested change to RESAST - to return correct values, in TEST (HRS092-8)
  • Implemented requested change to RESAST - to return correct values, in LIVE (HRS092-8)

Issues

  • Although the majority of REAST codes have been corrected, there are still a significant number of REAST with a code of 2 to be corrected

Next Steps

  • To fix the RESAST codes
  • Meeting arranged to discuss resourcing after April when current contract Developer leaves.
  • To revise project budget
  • Approve revised budget

Project has a RAG status of AMBER

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

AP67-035 Upgrade eRecruitment Database to Oracle 12c

CategoryL Compliance

This project has been withdrawn from the  current year as the end. of life for Oracle 11g has been extended till 2020 . There may be no requirement for the upgrade if erecruitment is replaced. This project will  therefore be planned for  18/19-19/20.

HRS090 (AP56-025)

HESA Staff Return 15/16

Category:Compliance

Report by Anne Mathisson

Project Closure Milestone achieved on 25-Nov-16, Project Completion Report available on the website

HRS086 eRecruitment Proof of Concept

Category: Discretionary, Funded

Report by Susan McKeown

Project Closure Milestone achieved on 25-Aug-15 Project's Completion Report is available on the website.

HRS085 HESA Staff Return 14/15

Category: Compliance

Report by Anne Mathison

Project Closure Milestone achieved on 20-Nov-15 Project's Completion Report is available on the website.

HRS087 HR Reward Calculator

Category: Funded

Report by Susan McKeown

Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website.

HRS088 HR Transformation: Governance and Planning

Category: Compliance

Report by Susan McKeown

Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website

HRS084 Enhancing Employment Analysis

Category: Discretionary

Report by Franck Bergeret

Project Closure Milestone achieved on 18-Feb-16 Project's Completion Report is available on the website

HRS090 HESA Staff Return 15/16

Category : Compliance

Report  by Anne Mathison

Project Closure Milestone achieved on 24-Nov-16 Project's Completion Report  is available on the website

AttachmentSize
Image icon hr-flook-april-2.jpg117.04 KB
Image icon hr-resources-april.jpg122.91 KB