Report for April 2017
- Report Date
- April 2017
Morna Findlay (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS089 - AMBER as closure milestone delayed.
HRS091 - RED as new budget and milestones approved and final report not signed off in LIVE
HRS092 - GREEN
Forward Look for April 2017
Resources to 30/04/2017
With the postponement until future years of the upgrade of Erecruitment to Oracle 12c, there are a significant number of days
remaining in the balance row which are currently unallocated. New in-year projects should fall under the compliance category and the
programme manager is exploring with the business whether the delivery of three reports dropped from HRS077 can be delivered in a new in-year project this year.
Section Two: Projects Not Started
There are no approved projects waiting to start.
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||
Category: Funded Milestones
RAG Status GREEN
|
Report by Muriel Mewissen for April 2017Achievements in the last period
Issues
Next Steps
|
||||||||||
Working Time Capture and Reporting ( was Enhancing Employment Technical Implementation) Category: Core Funded Compliance Milestones are draft and still to be agreed with the Project Sponsor 12/5/17 Fix for data issues complete 15/5/17 eTime Report re-tested 18/5/17 eTime Report Deployment complete 24/5/17 eTime Report Deployment Sign Off 31/5/17 Closure RAG Status RED |
Report by Susan Duff for April 2017Achievements in Last Period
Issues
- date search filter returning incorrect data over year end. Should be a month plus year start and end, ie. 4-2016 and 3-2017. Not high priority - report will run monthly. - job segment2 and org hierarchy queries will always return the value as at run date rather than date filter date. Next Period
Project has a RAG status of Red (cost) as additional days needed to resolve issue identified when report run on live data
|
||||||||||
HRS092 (AP67-034) HESA Staff Return 16/17 Category : Core-funded Compliance Milestones
RAG Status AMBER |
Report by Anne Mathison for April 2017Achievements:
Issues
Next Steps
Project has a RAG status of AMBER |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP67-035 Upgrade eRecruitment Database to Oracle 12c CategoryL Compliance |
This project has been withdrawn from the current year as the end. of life for Oracle 11g has been extended till 2020 . There may be no requirement for the upgrade if erecruitment is replaced. This project will therefore be planned for 18/19-19/20. |
Category:Compliance |
Report by Anne Mathisson Project Closure Milestone achieved on 25-Nov-16, Project Completion Report available on the website |
HRS086 eRecruitment Proof of Concept Category: Discretionary, Funded |
Report by Susan McKeown Project Closure Milestone achieved on 25-Aug-15 Project's Completion Report is available on the website. |
HRS085 HESA Staff Return 14/15 Category: Compliance |
Report by Anne Mathison Project Closure Milestone achieved on 20-Nov-15 Project's Completion Report is available on the website. |
Category: Funded |
Report by Susan McKeown Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website. |
HRS088 HR Transformation: Governance and Planning Category: Compliance |
Report by Susan McKeown Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website |
HRS084 Enhancing Employment Analysis Category: Discretionary |
Report by Franck Bergeret Project Closure Milestone achieved on 18-Feb-16 Project's Completion Report is available on the website |
HRS090 HESA Staff Return 15/16 Category : Compliance |
Report by Anne Mathison Project Closure Milestone achieved on 24-Nov-16 Project's Completion Report is available on the website |