Report for December 2016

Report Date
December 2016

Morna Findlay (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

 

Commentary

HRS089 - RED  (no issues) as milestones moved by more than one month (Approved)

HRS091 - RED - Revised project milestones and budget to be approved. Delivery expected in January.

 

Resources to 8/01/2017

 

 

The programme manager expects that more than 9 days will be required from the balance row to complete HRS089.

 

Forward Look for December  2016

 

 

 

 Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

AP67-034 HESA Staff Return 16/17

Core funded

Planning - April 2017

Delivery - Nov 2017

 RAG Status : GREEN

 Development team   working on plan to

resource HRS projects - see Risk 20

AP67-035 Upgrade eRecruitment Database to Oracle 12c

Core funded

Planning - Feb 2017

Delivery - Jul 2017

 RAG Status : GREEN

 

 

AP67-035 Upgrade eRecruitment Database to Oracle 12c

End of life for Oracle 11g has been extended to 2020. E-recruitment is on the last and latest supported version so there may be no need for this project.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HRS089 (AP56-907)

eRecruitment Upgrade

 

Category: Funded

Milestones

20-Jan-2017 Delivery Sign-off
17-Feb-2017 Closure

 

RAG Status

RED

 

Report by Muriel Mewissen for December 2016

Achievements in the last Period

  • Revised timeline and budget approved by the Project Sponsor
  • Minor update (v21.0.23) was installed and tested in DEV by CoreHR and made available for testing on 12 Dec to HR.
  • HR completed testing before Christmas closure and approved the deployment to TEST planned for January. Some Jiras can be closed because the issues have been addressed - some will remain until they can be tested in the LIVE system.

Issues

  • WIS approval for revised timeline not obtained because resource managers approval cannot be obtained before the Christmas closure.

Next Steps

  • Obtain approval for additional effort
  • Update to TEST & LIVE
  • Confirm resolution of all issues in LIVE
  • Project Closure

RAG stats: RED as new project estimate required

 

 

HRS091 (AP56-049)

Working Time Capture and Reporting ( was Enhancing Employment Technical Implementation)

Category: Discretionary

Milestones

Proposed revised milestones - resources to be confirmed and new dates agreed with Project Sponsor and approved by WIS

02-Dec-2016 APEX Report Deployment Sign Off
23-Dec-2016 eTime Report UAT complete
12-Jan-2017 eTime Report Acceptance Sign Off
17-Jan-2017 eTime Deployment complete
31-Jan-2017 eTime Report Deployment Sign Off
10-Feb-2017 Closure

RAG Status

RED

Report by Susan Duff for November 2016

Achievements in Last Period

  • APEX report build signed off
  • APEX report deployed to LIVE
  • Further business testing of eTime report completed
  • JIRAs for eTime progressed

Issues

  • Following initial testing of the eTime report, there are still issues to be resolved. Development resource needs to review the JIRAs and address the outstanding problems. The milestones need to be re-planned to reflect this. Proposed changes are below, subject to confirmation of Development resource availability and then agreement with the Project Sponsor. Issue open.

Next Period

  • APEX report deployment sign off to be completed
  • Revised milestones for the eTime report to be agreed
  • Outstanding issues with the eTime report to be resolved and retested

 

The project status is RED  to reflect requirement to delay milestones by more than one month.

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

HRS090 (AP56-025)

HESA Staff Return 15/16

Category:Compliance

Report by Anne Mathisson

Project Closure Milestone achieved on 25-Nov-16, Project Completion Report available on the website

HRS086 eRecruitment Proof of Concept

Category: Discretionary, Funded

Report by Susan McKeown

Project Closure Milestone achieved on 25-Aug-15 Project's Completion Report is available on the website.

HRS085 HESA Staff Return 14/15

Category: Compliance

Report by Anne Mathison

Project Closure Milestone achieved on 20-Nov-15 Project's Completion Report is available on the website.

HRS087 HR Reward Calculator

Category: Funded

Report by Susan McKeown

Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website.

HRS088 HR Transformation: Governance and Planning

Category: Compliance

Report by Susan McKeown

Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website

HRS084 Enhancing Employment Analysis

Category: Discretionary

Report by Franck Bergeret

Project Closure Milestone achieved on 18-Feb-16 Project's Completion Report is available on the website

HRS090 HESA Staff Return 15/16

Category : Compliance

Report  by Anne Mathison

Project Closure Milestone achieved on 24-Nov-16 Project's Completion Report  is available on the website