Report for December 2016
- Report Date
- December 2016
Morna Findlay (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS089 - RED (no issues) as milestones moved by more than one month (Approved)
HRS091 - RED - Revised project milestones and budget to be approved. Delivery expected in January.
Resources to 8/01/2017
The programme manager expects that more than 9 days will be required from the balance row to complete HRS089.
Forward Look for December 2016
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP67-034 HESA Staff Return 16/17 Core funded Planning - April 2017 Delivery - Nov 2017 RAG Status : GREEN |
Development team working on plan to resource HRS projects - see Risk 20 |
AP67-035 Upgrade eRecruitment Database to Oracle 12c Core funded Planning - Feb 2017 Delivery - Jul 2017 RAG Status : GREEN |
AP67-035 Upgrade eRecruitment Database to Oracle 12c
End of life for Oracle 11g has been extended to 2020. E-recruitment is on the last and latest supported version so there may be no need for this project.
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||
Category: Funded Milestones
RAG Status RED
|
Report by Muriel Mewissen for December 2016Achievements in the last Period
Issues
Next Steps
RAG stats: RED as new project estimate required
|
||||||||||||
Working Time Capture and Reporting ( was Enhancing Employment Technical Implementation) Category: Discretionary Milestones Proposed revised milestones - resources to be confirmed and new dates agreed with Project Sponsor and approved by WIS
RAG Status RED |
Report by Susan Duff for November 2016Achievements in Last Period
Issues
Next Period
The project status is RED to reflect requirement to delay milestones by more than one month. |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Category:Compliance |
Report by Anne Mathisson Project Closure Milestone achieved on 25-Nov-16, Project Completion Report available on the website |
HRS086 eRecruitment Proof of Concept Category: Discretionary, Funded |
Report by Susan McKeown Project Closure Milestone achieved on 25-Aug-15 Project's Completion Report is available on the website. |
HRS085 HESA Staff Return 14/15 Category: Compliance |
Report by Anne Mathison Project Closure Milestone achieved on 20-Nov-15 Project's Completion Report is available on the website. |
Category: Funded |
Report by Susan McKeown Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website. |
HRS088 HR Transformation: Governance and Planning Category: Compliance |
Report by Susan McKeown Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website |
HRS084 Enhancing Employment Analysis Category: Discretionary |
Report by Franck Bergeret Project Closure Milestone achieved on 18-Feb-16 Project's Completion Report is available on the website |
HRS090 HESA Staff Return 15/16 Category : Compliance |
Report by Anne Mathison Project Closure Milestone achieved on 24-Nov-16 Project's Completion Report is available on the website |
Attachment | Size |
---|---|
![]() | 94.8 KB |
![]() | 60.3 KB |