Report for November 2016
- Report Date
- November 2016
Morna Findlay (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS089 - RED - Multiple JIRAs in LIVE require fixes from supplier, now expected to be deployed in January. Revised milestones to be approved.
HRS090 - GREEN - Project closed.
HRS091 - RED - Revised project milestones and budget to be approved. Delivery expected in January.
Resources to 2/12/2016
Forward Look for November 2016
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP67-034 HESA Staff Return 16/17 Core funded Planning - April 2017 Delivery - Nov 2017 RAG Status : GREEN |
Development team working on plan to resource HRS projects - see Risk 20 |
AP67-035 Upgrade eRecruitment Database to Oracle 12c Core funded Planning - Feb 2017 Delivery - Jul 2017 RAG Status : GREEN |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||
Category: Funded Milestones
RAG Status RED
|
Report by Muriel Mewissen for November 2016Achievements in the last Period
Issues
Next Steps
The project RAG status is RED as new estimate and milestones need to be approved by sponsor.
|
||||||||||||
Category: Compliance Milestones None
RAG Status BLUE |
Report by Anne Mathison for November 2016Achievements: -
Issues
Next Steps
HRS090 now has a BLUE RAG status |
||||||||||||
Working Time Capture and Reporting ( was Enhancing Employment Technical Implementation) Category: Discretionary Milestones Proposed revised milestones - resources to be confirmed and new dates agreed with Project Sponsor and approved by WIS
RAG Status RED |
Report by Susan Duff for November 2016Achievements in Last Period
Issues
Next Period
The project status is RED to reflect requirement to delay milestones by more than one month. |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
HRS086 eRecruitment Proof of Concept Category: Discretionary, Funded |
Report by Susan McKeown Project Closure Milestone achieved on 25-Aug-15 Project's Completion Report is available on the website. |
HRS085 HESA Staff Return 14/15 Category: Compliance |
Report by Anne Mathison Project Closure Milestone achieved on 20-Nov-15 Project's Completion Report is available on the website. |
Category: Funded |
Report by Susan McKeown Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website. |
HRS088 HR Transformation: Governance and Planning Category: Compliance |
Report by Susan McKeown Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website |
HRS084 Enhancing Employment Analysis Category: Discretionary |
Report by Franck Bergeret Project Closure Milestone achieved on 18-Feb-16 Project's Completion Report is available on the website |
HRS090 HESA Staff Return 15/16 Category : Compliance |
Report by Anne Mathison Project Closure Milestone achieved on 24-Nov-16 Project's Completion Report is available on the website |