Report for November 2016

Report Date
November 2016

 

Morna Findlay (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

 

Commentary

HRS089 - RED - Multiple JIRAs in LIVE require fixes from supplier, now expected to be deployed in January.  Revised  milestones to be approved.

HRS090 - GREEN - Project closed.

HRS091 - RED - Revised project milestones and budget to be approved. Delivery expected in January.

 

Resources to 2/12/2016

 

Resources November

 

 

Forward Look for November  2016

 

Forward Look November 2016

 

 

 

 Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

AP67-034 HESA Staff Return 16/17

Core funded

Planning - April 2017

Delivery - Nov 2017

 RAG Status : GREEN

 Development team   working on plan to

resource HRS projects - see Risk 20

AP67-035 Upgrade eRecruitment Database to Oracle 12c

Core funded

Planning - Feb 2017

Delivery - Jul 2017

 RAG Status : GREEN

 

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HRS089 (AP56-907)

eRecruitment Upgrade

 

Category: Funded

Milestones

20-Jan-2017 Delivery Sign-off
17-Feb-2017 Closure

 

RAG Status

RED

 

Report by Muriel Mewissen for November 2016

Achievements in the last Period

  • Muriel Mewissen took over Susan Mckeown as the new PM for this project on 17 November 2016.
  • The Jiras for major issues have now been fixed, and a patch to the DEV & TEST environments has been scheduled. This was first due on the 22 Nov, later pushed back to the 24 Nov. But during the testing of the patch on a copy of the database provided by UoE, further issues were uncovered. These issues are addressed in a minor update (V21) to be released on the 6 Dec. 
  • A new timeline has been agreed to update installation to V21, then apply and test the patch.

Issues

  • Further delays caused by more issues being found, and require milestones to be reviewed (see issue 14):

    • The update and patching of DEV will take place w/c 5 Dec.
    • The update and patching of TEST will take place w/c 2 Jan.
    • System to be LIVE w/c 17 Jan.
  • The previously agreed budget was reached last month. New PM and delays means the budget needs to be increased by an estimated 24 days to take the project to closure. This is awaiting Sponsor agreement.

Next Steps

  • Obtain approval for additional effort and reviewed delivery date
  • Resolution of minor issues Jiras
  • Project Closure

 

The project RAG status is RED as new estimate and milestones need to be approved by sponsor.

 

HRS090 (AP56-025)

HESA Staff Return 15/16

Category: Compliance

Milestones

None

 

RAG Status

BLUE

Report by Anne Mathison for November 2016

Achievements: -

  • HESA finally submitted before 11-Nov
  • Completion Report circulated and signed off
  • Project was closed by 25th November and agreed at WIS 2-Dec-16

Issues

  • None

Next Steps

  • None

HRS090 now has a BLUE RAG status

 

HRS091 (AP56-049)

Working Time Capture and Reporting ( was Enhancing Employment Technical Implementation)

Category: Discretionary

Milestones

Proposed revised milestones - resources to be confirmed and new dates agreed with Project Sponsor and approved by WIS

02-Dec-2016 APEX Report Deployment Sign Off
23-Dec-2016 eTime Report UAT complete
12-Jan-2017 eTime Report Acceptance Sign Off
17-Jan-2017 eTime Deployment complete
31-Jan-2017 eTime Report Deployment Sign Off
10-Feb-2017 Closure

RAG Status

RED

Report by Susan Duff for November 2016

Achievements in Last Period

  • APEX report build signed off
  • APEX report deployed to LIVE
  • Further business testing of eTime report completed
  • JIRAs for eTime progressed

Issues

  • Following initial testing of the eTime report, there are still issues to be resolved. Development resource needs to review the JIRAs and address the outstanding problems. The milestones need to be re-planned to reflect this. Proposed changes are below, subject to confirmation of Development resource availability and then agreement with the Project Sponsor. Issue open.

Next Period

  • APEX report deployment sign off to be completed
  • Revised milestones for the eTime report to be agreed
  • Outstanding issues with the eTime report to be resolved and retested

 

The project status is RED  to reflect requirement to delay milestones by more than one month.

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

HRS086 eRecruitment Proof of Concept

Category: Discretionary, Funded

Report by Susan McKeown

Project Closure Milestone achieved on 25-Aug-15 Project's Completion Report is available on the website.

HRS085 HESA Staff Return 14/15

Category: Compliance

Report by Anne Mathison

Project Closure Milestone achieved on 20-Nov-15 Project's Completion Report is available on the website.

HRS087 HR Reward Calculator

Category: Funded

Report by Susan McKeown

Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website.

HRS088 HR Transformation: Governance and Planning

Category: Compliance

Report by Susan McKeown

Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website

HRS084 Enhancing Employment Analysis

Category: Discretionary

Report by Franck Bergeret

Project Closure Milestone achieved on 18-Feb-16 Project's Completion Report is available on the website

HRS090 HESA Staff Return 15/16

Category : Compliance

Report  by Anne Mathison

Project Closure Milestone achieved on 24-Nov-16 Project's Completion Report  is available on the website

 

AttachmentSize
Image icon Resources November139.76 KB