Report for May 2018

Report Date
May 2018

For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.Section One: Programme Commentary, RAG and Resources Update

 

During May,

From a programme perspective;

The only current activity is centred around the project ACS039 - Kx Infrastructure Consolidation.

The Kx Modules Upgrades Placeholder project has been withdrawn   

The 10 days remaining in the Sponsor Funded balance have been removed as they will not be required.  As a result the overall programme budget has been reduced to 81 days for this year. 

Forward Look 

Resource Position 

 

Section Two: Projects Not Started

 

The scheduled projects for 2017-18 are:

 

Project Info Programme Managers Commentary

 

 

No further projects planned for 2017/18

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ACS039

Kx Infrastructure Consolidation 

Category: Discretionary

Sponsor Funded

Milestones

Target Date Title
15-Jun-2018 Closure

 

RAG Status

Amber

 

 

Report by Andy Stewart  for May 2018

Achievements in the last period

  • The Technical Architecture Document (TAD) has been updated and circulated for feedback
  • The Operations Level Document (OLA) has been updated and circulated for feedback
  • Audit of Kx servers undertaken and redundant servers identified in preparation for de-commission
  • First draft of project closure document circulated and subsequently approved by Project Sponsor

Issues

  • Project extended to 15/06/18 to enable the TAD and OLA to be competed

Next steps

  • Sign-off TAD
  • Sign-off OLA
  • Sign-off Project Closure report
  • Close project

RAG Status: Amber Change: Project closure date extended to 15/06 to enable the TAD and OLA documentation to be completed

 

 

 

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary
ACS037

Cashless Catering Upgrade 

Project withdrawn on 18th August 

Project Completion Report 

ACS036

Kx Database Infrastructure Upgrade

Project closed on 22/09/2017

Project Completion Report

AP56-059

Delivered Catering External

Project withdrawn on 12/01/2018

 

Kx Modules Upgrades Placeholder

Project withdrawn on 11/05/18

 

Section Five: Programme Risks

Date Updated Risk Ref. Programme Risks RAG Status Risk Owner
12/06/18 6

Programme Management budget for 2017-18 being exceeded For the March report, the usage (11 days) is currently over with the predicted spend (10 days)

Green Andrew Stewart

Section Six : Programme Meeting Minutes

 This section details the minutes from the programme meetings

Date Comments
14/12/16 Minutes from November Programme Meeting
16/11/16 Minutes from October Programme Meeting
16/11/16 Minutes from In-Year Project Review Meeting
12/10/16 Minutes from September Programme Meeting
14/09/16 Minutes from August Programme Meeting
15/08/16 Minutes from 2016-17 Projects Review and Planning Meeting
18/05/16 Minutes from Programme Meeting
02/12/15 Minutes from Programme Review Meeting
11/11/15 Minutes from Programme Meeting
16/09/15 Minutes from Programme Meeting
12/07/17 Minutes from Programme Meeting 
13/09/17 Minutes from Programme Meeting
AttachmentSize
Image icon 201805-rag.png24.64 KB
Image icon 201805-resources.png28.3 KB

Documentation

Not available.