October 2019

Report Date
October 2019

Amber. There are delays in recruiting staff to start the new funded project. Aim to start once new BA has been recruited

Project Status
RAG Status
Overall
AMBER
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation