October 2019

Report Date
October 2019

Achievements this period

  • All environments in place as requested
  • DEV Finish Up for two DEV servers required some more time as expected
  • Milestones were adjusted accordingly without affecting the Live Release date
  • Closing Date was brought forward for the end of 2019

Issues

  • DEV Built Phase required more time than expected and is delaying the completion of the Built stage
  • Project manager has left the project  (conflict with Core systems)-Decision made to complete the current task, i.e. to complete the 1st server upgrade (Dev). Then consider options to continue or suspend project. The implementation window is closing and the option is to restart the project after the SITS software upgrade  in May/June 2020 

Next Steps

  • TAD to be provided from DevTech to TechManagement
  • DEV Built to be finished up and tested
  • TEST Built to be started
  • LIVE Server to be requested from ITI
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
Red as the project manager has left the project (conflict with core systems). Project stage: build. Option to suspend project is being considered if new servers is not signed off early Nov. Impact of industrial action to go live unknown. Small window to go live. Impact to SSP Dev team leader workload to coordinate remaining work.
Change Status
Has formal escalation taken place?
Yes
Escalated to
SSP senior supplier
Activity
Approved budget
105.0 days
Activity this month
20.0 days
Activity this year
50.0 days
Activity to date
59.0 days
Estimate to complete current year
31.0 days
Estimate to complete future years
0.0 days